Summary Information
- Ownership: Saudi Aramco
- Website: https://www.aramco.com/
- Location: Eastern Province of Saudi Arabia
- Capacity: 2.5 billion standard cubic feet per day (bscfd)
Brief Description
- Fadhili was the first plant to treat non-associated gas from both onshore and offshore fields, and the first Aramco plant designed from the start to use Tail Gas Treatment technology.
- The plant processes a total of 2.5 billion SCFD of non-associated gas and produces 1.5 billion SCFD of sales gas, while also supplying an adjacent cogeneration power plant, which provides Fadhili with power and steam requirements, and also supplies about 1,100 megawatts of electricity to the domestic grid.
- It also produces 4,000 metric tons per day of Sulphur
Related Oil and Gas Fields
- It processes gas from the Hasbah Gas Field and the Khursaniyah Oil and Gas Field
Ongoing Projects
- The Fadhili Gas Plant Increment Project will add up to 1.5 billion standard cubic feet per day to the capacity by 2027
Other Information
- -
History
- 2016 - EPC contracts were signed for the project
- 2019 - Phase one of the project was completed
- 2020 - Plant reaches design capacity