Brief Description

  • The terminal utilises the Floating Storage and Regasification Unit (“FSRU”) Energos Winter which has the capacity to store 160,000 cubic meters of LNG.
  • The TGS will be located 300 meters from the coast.
  • After regasification, the natural gas continues for about 2 kilometers in a pipeline under the bed of the bay, until it flows into the same entry point of the OSPAR pipeline, in Itapoá

Technical Details

  • Storage capacity: 160,000 cubic meters
  • Unloading capacity:
  • Send out capacity:
  • Constructor: Tenenge built the connections to the local grid

Ongoing Projects/Project Status

  • The terminal is scheduled to start operations in January 2024.

Suppliers / Customers

  • Suppliers:
  • Customers:

History

  • 2021 - Construction was started
  • 2023 - Charter signed for FSRU vessel

Other Information

-

Links

  1. Terminal Page, New Fortress Energy

https://abarrelfull.blogspot.com/2023/11/tenenge-starts-construction-of-gas.html Tenenge starts construction of Gas Terminal in Santa Catarina]

  1. New Fortress Energy Signs FSRU Charter to Start Operations of LNG Import Terminal in Santa Catarina, Brazil in January 2024