Summary Information
- Source:
- Destination: Guadalajara, Mexico
- Ownership: Transcanada
- Website: http://www.transcanada.com/
- Length: 307- kilometres (192 miles)
- Capacity: 820 million cubic feet of natural gas per day
- Status: Operating
Details
- The Guadalajara Pipeline connects to an [[[Manzanillo LNG terminal | LNG regasification facility located near Manzanillo]]] on the Pacific Coast of Mexico in the state of Colima. It has capacity to transport 500 million cubic feet of natural gas per day to a nearby power plant owned by Comisión Federal de Electricidad (CFE) and 320 million cubic feet per day to the Pemex-owned national pipeline system near Guadalajara in the state of Jalisco in Mexico's interior.
History
- 2009 - The Comisión Federal de Electricidad (CFE) awarded the Guadalajara Project to Energía Occidente de México, S. de R.L. de C.V. (EOM), a wholly owned TransCanada affiliate
- 2011 - TransCanada announces completion of the Guadalajara Pipeline
Other Information
- -