Jasmine Gas and Condensate Field
Revision as of 22:36, 30 November 2021 by Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Operator: ConocoPhillips * Country: UK * Location: blocks P011 and P0032 30/7a, Central North Sea * Production start: 2013 * Partners: ConocoPhil...")
Summary Information
- Operator: ConocoPhillips
- Country: UK
- Location: blocks P011 and P0032 30/7a, Central North Sea
- Production start: 2013
- Partners: ConocoPhillips - 36.5, BG Group - 30.5%, ENI - 33.0%
- Type: Gas And Condensate
- Estimated Reserves: recoverable reserves are estimated at around 170 mmboe
- Production Volume:
Description
- Jasmine is a high pressure, high temperature (HP/HT) gas-condensate reservoir
- The Jasmine development, located approximately 5.5 miles west of the Judy production facility, comprises a Jasmine wellhead platform (WHP) and an accommodation and utility platform bridge-linked to the WHP; a Judy riser and separation platform (JRP) with additional Judy well slots bridge-linked to the existing Judy platform; and a multiphase pipeline from the WHP to the JRP.
- From [[[Judy Joanne And Jade Gas And Condensate Fields | Judy]]], gas is trasported via the [[[CATS Central Area Transmission System Gas Pipeline]]] to the [[[Teesside Gas Processing Plant TGPP]]]
Contractors
- **Halliburton:** Directional drilling, logging-while-drilling (LWD) and surface data logging (SDL) services
- **Dragados Offshore:** Constructability analysis, construction engineering, partial purchases, construction, commissioning, load out and sea fastening of two decks
- **WorleyParsons:** Detailed engineering for three platforms, interconnecting bridges, pipe-in-pipe risers and spools along with the functional design and specification for the subsea pipeline, subsea isolation valves, power/communications cable and umbilicals
- **Subsea 7:** Engineering, procurement, fabrication, installation and commissioning of two approximately 4km pipeline bundle systems and associated pipe-in-pipe spools
- **AMEC:** Detailed engineering and procurement the existing Judy platform and the hook-up and commissioning of their new Jasmine facilities
- **Rosetti Marino:**
* Procurement, Construction and Commissioning of Topsides for the Jasmine platform * Construction engineering, procurement, fabrication, load-out and sea-fastening of JASMINE WHP, JLQ & JRP substructures
- **IKM Testing:** Pressure Tests, Bolt Tensioning & Torquing, Hot Oil Flushing, Cleaning, Video Inspection, Test Engineering, Drying & N2 Purging
- **Saipem:** Wellhead, accomodation and process platforms
- **FoundOcean:** Grouting for Jasmine Living Quarters & WHP
- **KWSubsea:** Pipeline Concept Engineering Services
History
- 2006 - Jasmine Gas And Condensate Field discovered
- 2010 - WorleyParsons awarded Detailed engineering contract
- 2010 - Halliburton awarded drilling contract
- 2010 - Dragados Offshore awarded deck contract
- 2013 - First gas produced
- 2017 - Chrysaor acquired Shell's stake in the field.
Geology
Links
- Central North Sea, ConocoPhillips
- [[[List Of Oil and Gas Production Platforms In The UK]]]
- [[[Saipem Fixed Offshore Production Facilities Project References]]]
- [[[FoundOcean Subsea References]]]
- [[[KWSubsea Subsea References]]]
- [[[Rosetti Marino Platform References]]]
- BG Group announce substantial North Sea discovery
- Subsea 7 Confirms Contract for ConocoPhillips Jasmine Discovery in the North Sea
- IKM Testing Spain awarded a new contract
- Halliburton Wins Contract for Jasmine
- Award by ConocoPhillips for Jasmine Area Development
- AMEC awarded Judy and Jasmine contract North Sea
- Conocophilips Awards A New Contract To Dragados Offshore
- First gas production from UK Jasmine field
- Shell to sell package of UK North Sea assets to Chrysaor for up to $3.8bn