Huelva LNG Terminal
Revision as of 14:04, 19 February 2023 by Abarrelfull (talk | contribs)
Summary Information
- Ownership: Enagas
 - Website: http://www.enagas.es/
 - Location: The plant is located at the mouth of the rivers Tinto and Odiel, Huelva
 - Capacity: million tons/annum
 - Status: In Operation
 
+++ Brief Description
- A large regasification terminal
 
+++ Technical Details
- Storage capacity: 60,000 m3 + 105,000 m3 + 2 * 150,000 m3
 - Unloading capacity:
 - Send out capacity:
 - Constructor:
 
* Expansion: * **Foster Wheeler** - Detailed engineering, equipment and material procurement, and construction supervision * **Freyssinet:** Pre-stressing for LNG tanks 3,4 &5 * **Saipem:** Construction of tanks 3 & 4
+++ Ongoing Projects/Project Status
- A fifth tank of capacity 150.000 m3 is under construction
 
+++ Suppliers / Customers
- Suppliers:
 - Customers:
 
+++ History
- 1988 - Terminal commences operations with a single tank of 60,000 m3
 - 1992 - The second tank (105,000 m3) came into operation
 - 2002 - Foster Wheeler awarded detailed engineering, equipment and material procurement, and construction supervision for expansion
 - 2004 - The third tank (150,000 m3) came into operation
 - 2006 - The fourth tank (150,000 m3) came into operation
 
+++ Other Information
- -
 
+++ Relevant Links
- Terminal Webpage
 - [[[Freyssinet LNG Tank References]]]
 - [[[Saipem LNG References]]]
 - Foster Wheeler Iberia Wins Two LNG Terminal Expansion Projects in Spain