Windermere Gas Field
Revision as of 13:23, 11 June 2024 by Abarrelfull (talk | contribs)
Summary Information
- Operator: Ineos
- Country: UK
- Location:
- Production start:
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- The Windermere development is a gas producing normally unattended installation (NUI) located in SNS Block 49/09b
- The Windermere platform is a fixed three-legged jacket
- The platform is tied back via a 7 kilometre long 8-inch pipeline to the Centrica Energy Upstream (Centrica), operated ST-1 platform that is part of the Markham Gas Field complex
Contractors
- -
History
- 1996 - Development approval granted
- 1997 - The Windermere platform was installed
- 1997 - First gas produced
- 2015 - Ineos acquired the field from DEA
- 2016 - Production ceased
- 2021 - Approval granted for decommissioning
Geology
- A thin, basal aeolian sandstone is top-sealed by lacustrine Silverpit Formation, clay stones and sourced by the underlying Westphalian Coal Measures.