Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Ownership: OLT Offshore LNG Toscana (IREN GROUP, E.ON GROUP) * Website: http://www.oltoffshore.it/ * Location: Livorno, Tuscany, Italy * Capaci...") |
Abarrelfull (talk | contribs) |
||
| Line 7: | Line 7: | ||
* Status: In operation | * Status: In operation | ||
| − | + | === Brief Description === | |
* The terminal a floating regasification unit, created by modifying an LNG carrier, which is positioned 22 km offshore the Tuscan coast and is connected to dry land by a 30 km long pipeline for the transfer of the gas to the national distribution system. | * The terminal a floating regasification unit, created by modifying an LNG carrier, which is positioned 22 km offshore the Tuscan coast and is connected to dry land by a 30 km long pipeline for the transfer of the gas to the national distribution system. | ||
* The vessel is moored with an external turret in 120 m water depth | * The vessel is moored with an external turret in 120 m water depth | ||
| Line 13: | Line 13: | ||
| − | + | === Technical Details === | |
* Storage capacity: 137,500 cubic metres | * Storage capacity: 137,500 cubic metres | ||
* Unloading capacity: | * Unloading capacity: | ||
* Send out capacity: 3.75 billion cubic meters a year | * Send out capacity: 3.75 billion cubic meters a year | ||
* Constructor: | * Constructor: | ||
| − | + | ** '''Saipem:''' Conversion of the gas carrier ship, offshore installation and commissioning | |
| − | + | ** '''Drydocks World:''' Vessel conversion | |
| − | + | ** '''London Marine:''' Turret Mooring System | |
| − | + | === Ongoing Projects/Project Status === | |
| − | * Completed in | + | * Completed in [[LNG Terminal Projects Completed in 2013 | 2013]] |
| − | + | === Suppliers / Customers === | |
* Suppliers: | * Suppliers: | ||
* Customers: OLT has signed a deal with the city of Livorno to supply gas | * Customers: OLT has signed a deal with the city of Livorno to supply gas | ||
| − | + | === History === | |
* 2004 - The project received its final environmental approval | * 2004 - The project received its final environmental approval | ||
* 2008 - Vessel purchased from Golar LNG | * 2008 - Vessel purchased from Golar LNG | ||
| Line 38: | Line 38: | ||
* 2013 - FSRU is commissioned | * 2013 - FSRU is commissioned | ||
| − | + | === Other Information === | |
* - | * - | ||
Revision as of 13:36, 11 December 2025
Contents
Summary Information
- Ownership: OLT Offshore LNG Toscana (IREN GROUP, E.ON GROUP)
- Website: http://www.oltoffshore.it/
- Location: Livorno, Tuscany, Italy
- Capacity: 3 million tons/annum
- Status: In operation
Brief Description
- The terminal a floating regasification unit, created by modifying an LNG carrier, which is positioned 22 km offshore the Tuscan coast and is connected to dry land by a 30 km long pipeline for the transfer of the gas to the national distribution system.
- The vessel is moored with an external turret in 120 m water depth
- The vessel Golar Frost was converted
Technical Details
- Storage capacity: 137,500 cubic metres
- Unloading capacity:
- Send out capacity: 3.75 billion cubic meters a year
- Constructor:
- Saipem: Conversion of the gas carrier ship, offshore installation and commissioning
- Drydocks World: Vessel conversion
- London Marine: Turret Mooring System
Ongoing Projects/Project Status
- Completed in 2013
Suppliers / Customers
- Suppliers:
- Customers: OLT has signed a deal with the city of Livorno to supply gas
History
- 2004 - The project received its final environmental approval
- 2008 - Vessel purchased from Golar LNG
- 2008 - Saipem awarded conversion & installation contract
- 2010 - Offshore pipeline laying completed
- 2013 - FSRU is commissioned
Other Information
- -
Links
- London Marine FPSO References
- Saipem LNG References
- Saipem FPSO References
- Saipem Europe Pipeline References
- International Protective Coatings Floating Platform Referenc
- Floating Storage & Regasification Unit, Golar LNG
- Livorno FSRU Project - Golar Frost Sale
- Saipem awarded new Offshore contract worth 390 million euro
- The offshore works which concerned laying and burying the offshore pipeline were ended as scheduled
- Fairmount Tugs Deliver Floating 'Gas Plant' Toscana
- Commissioning of the Terminal “FSRU Toscana” is proceeding
- Testing activities of the Terminal "FSRU Toscana" are going to be completed
- The commercial activities of the Terminal; FSRU Toscana; has been started