Difference between revisions of "Bacalhau Oil Field"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) (→Links) |
Abarrelfull (talk | contribs) |
||
Line 16: | Line 16: | ||
* Modec: Pre-Front End Engineering Design (Pre-FEED) and turnkey contractor for the FPSO | * Modec: Pre-Front End Engineering Design (Pre-FEED) and turnkey contractor for the FPSO | ||
* Aibel: FEED phase for management and basic engineering services & EPC contract including detail engineering, bulk procurement and construction of topside modules | * Aibel: FEED phase for management and basic engineering services & EPC contract including detail engineering, bulk procurement and construction of topside modules | ||
+ | * Subsea Integration Alliance: engineering, procurement, construction, and installation (EPCI) of the subsea production systems (SPS) and subsea pipelines (SURF) | ||
=== History === | === History === |
Revision as of 15:03, 21 April 2022
Summary Information
- Operator: Equinor
- Country: Brazil
- Location: Located 185 km from the coast of the municipality of Ilhabela/SP, in the state of São Paulo
- Production start: Expected 2024
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume: phase 1 est 220,000 bpd
Description
- The Bacalhau field is situated across two licenses, BM-S-8 and Norte de Carcará.
- The development will consist of 19 subsea wells tied back to a floating production, storage and offloading unit (FPSO) located at the field. This will be one of the largest FPSOs in Brazil with a production capacity of 220,000 barrels per day and two million barrels in storage capacity. The stabilized oil will be offloaded to shuttle tankers and the gas from Phase 1 will be re-injected in the reservoir.
Contractors
- Modec: Pre-Front End Engineering Design (Pre-FEED) and turnkey contractor for the FPSO
- Aibel: FEED phase for management and basic engineering services & EPC contract including detail engineering, bulk procurement and construction of topside modules
- Subsea Integration Alliance: engineering, procurement, construction, and installation (EPCI) of the subsea production systems (SPS) and subsea pipelines (SURF)
History
- 2012 - Bacalhau Oil Field was discovered by Petrobras
- 2016 - Equinor became operator
- 2018 - MODEC was awarded a Pre-Front End Engineering Design (Pre-FEED) contract for the FPSO
- 2020 - MODEC was awarded turnky contract for the FPSO
- 2021 - Final investment decision
Geology
- The resource is a high-quality carbonate reservoir, containing light oil with minimal contaminants