Difference between revisions of "Penguins FPSO"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) (→Links) |
Abarrelfull (talk | contribs) |
||
Line 26: | Line 26: | ||
* 2018 - Fluor awarded engineering, procurement and fabrication contract | * 2018 - Fluor awarded engineering, procurement and fabrication contract | ||
* 2023 - Aibel receives commissioning contract | * 2023 - Aibel receives commissioning contract | ||
+ | * 2025 - Penguins FPSO starts production | ||
=== Other Information === | === Other Information === |
Latest revision as of 10:04, 17 March 2025
Contents
Summary Information
- Name: Penguins FPSO
- Field: Penguins Oil Field
- Country: United Kingdom
- Ownership: Shell
- Website:
- Field Operated By: Shell
- Capacity: 45,000 bpd
- Year of Completion: 2023
Brief Description
- The vessel is of a cylindrical design, with production capacity of 45,000 barrels of oil equivalent per day with storage capability of up to 400,000 barrels
- The Penguins FPSO is 130 metres high and weighs 32,000 tonnes.
Contractors
- Fluor: Engineering, procurement and fabrication of the floating production storage and offloading (FPSO) vessel
- CIMC Raffles: Construction of the hull
- Aibel: Preparation for arrival, temporary construction activities and commissioning assistance
Status
- Due to be commissioned in 2024
History
- 2018 - Fluor awarded engineering, procurement and fabrication contract
- 2023 - Aibel receives commissioning contract
- 2025 - Penguins FPSO starts production
Other Information
- -