Difference between revisions of "Alma and Galia Oil Fields"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
| Line 41: | Line 41: | ||
# [http://killajoules.wikidot.com/blog:3508 Jumbo main installation contractor for EnQuest Producer] | # [http://killajoules.wikidot.com/blog:3508 Jumbo main installation contractor for EnQuest Producer] | ||
# [http://killajoules.wikidot.com/blog:5112 Jumbo installs North Sea FPSO mooring spread] | # [http://killajoules.wikidot.com/blog:5112 Jumbo installs North Sea FPSO mooring spread] | ||
| + | # [https://abarrelfull.blogspot.com/2024/05/almagalia-first-oil.html Alma/Galia first oil] | ||
| + | |||
| + | [[category:Field]] | ||
| + | [[category:UK]] | ||
| + | [[category:EnQuest]] | ||
Revision as of 12:06, 29 May 2024
Summary Information
- Operator: EnQuest
- Country: UK
- Location: North Sea
- Production start: 2015
- Partners:
- Type: Oil
- Estimated Reserves:
- Production Volume:
Description
- The Alma/Galia fields are located in blocks 30/24c and 30/25c respectively, 310km southeast of Aberdeen, in the Central North Sea.
- Production is via the EnQuest Producer Floating Production, Storage and Offloading vessel Enquest Producer FPSO
- The field were previously called Duncan and Argyll Oil Fields
Contractors
- **Technip:**
- Installation of two 10” production flexible flowlines, one 8” water injection flexible flowline and one further 8” production flexible flowline,
- Installation of three 8” flexible risers,
- Installation of two production control umbilicals/risers,
- Installation of four power cables and associated dynamic risers,
- Procurement, fabrication and installation of a 175 ton manifold structure,
- Associated trenching operations, tie-ins, testing and commissioning.
- **Jumbo:** FPSO mooring, installation and hook-up contract
History
- 1983 - Duncan field development approved
- 1992 - Decommissioning was approved for the Duncan and Argyll Oil Fields
- 2012 - Field development approval given
- 2012 - Technip awarded subsea contract
- 2012 - Jumbo awarded FPSO mooring, installation and hook-up contract
- 2014 - FPSO mooring spread installed
- 2015 - First oil produced