Line 5: | Line 5: | ||
* Location: Brownsville, Texas | * Location: Brownsville, Texas | ||
* Capacity: 27.5 million tons/annum | * Capacity: 27.5 million tons/annum | ||
− | * Status: | + | * Status: Under construction |
=== Brief Description === | === Brief Description === | ||
* The Rio Grande LNG project includes plans for up to six liquefaction trains, each with a nominal output capacity of 4.5 million tons of LNG per train per year | * The Rio Grande LNG project includes plans for up to six liquefaction trains, each with a nominal output capacity of 4.5 million tons of LNG per train per year | ||
− | * Phase 1 includes the first 3 trains and FID | + | * Phase 1 includes the first 3 trains and FID was taken in 2023 |
− | * Phase 2 includes trains 4 & 5 | + | * Phase 2 includes trains 4 & 5 and FID is expected in 2024 |
− | * Gas is to be supplied via | + | * Gas is to be supplied via the [[Rio Bravo Gas Pipeline]] from the [[Agua Dulce Natural Gas Hub]] |
=== Technical Details === | === Technical Details === | ||
Line 30: | Line 30: | ||
** Itochu - 1.0 mtpa | ** Itochu - 1.0 mtpa | ||
** Total - 5.4 mtpa | ** Total - 5.4 mtpa | ||
+ | ** ADNOC - 1.9mtpa from train 4 | ||
=== History === | === History === | ||
Line 40: | Line 41: | ||
* 2023 - Global Infrastructure Partners (GIP) and TotalEnergies agree to take stakes in phase 1 | * 2023 - Global Infrastructure Partners (GIP) and TotalEnergies agree to take stakes in phase 1 | ||
* 2023 - Final investment decision taken for phase 1 | * 2023 - Final investment decision taken for phase 1 | ||
+ | * 2024 - ADNOC announced the acquisition of a 11.7% stake in Phase 1 and a 1.9ntpa take off agreement | ||
+ | * 2025 - Baker Hughes awarded contract for gas turbine and refrigerant compressors for trains 4-8 | ||
=== Other Information === | === Other Information === | ||
Line 45: | Line 48: | ||
=== Links === | === Links === | ||
+ | # [[Long Term Applications Received by DOE/FE]] | ||
# [http://killajoules.wikidot.com/archive:rio-grande-lng-submits-official-pre-file-request-to Rio Grande LNG Submits Official Pre-File Request to the FERC and Receives Notification of Acceptance] | # [http://killajoules.wikidot.com/archive:rio-grande-lng-submits-official-pre-file-request-to Rio Grande LNG Submits Official Pre-File Request to the FERC and Receives Notification of Acceptance] | ||
# [http://killajoules.wikidot.com/blog:5884 CB&I Announces Contract for Rio Grande LNG Project] | # [http://killajoules.wikidot.com/blog:5884 CB&I Announces Contract for Rio Grande LNG Project] | ||
Line 56: | Line 60: | ||
# [https://lng-news.blogspot.com/2023/07/nextdecade-announces-positive-final.html NextDecade Announces Positive Final Investment Decision on Rio Grande LNG Phase 1] | # [https://lng-news.blogspot.com/2023/07/nextdecade-announces-positive-final.html NextDecade Announces Positive Final Investment Decision on Rio Grande LNG Phase 1] | ||
# [https://lng-news.blogspot.com/2023/08/air-products-lng-liquefaction.html Air Products’ LNG Liquefaction Technology and Equipment Selected for NextDecade’s Rio Grande LNG Project] | # [https://lng-news.blogspot.com/2023/08/air-products-lng-liquefaction.html Air Products’ LNG Liquefaction Technology and Equipment Selected for NextDecade’s Rio Grande LNG Project] | ||
+ | # [https://lng-news.blogspot.com/2024/05/adnoc-secures-equity-position-and-lng.html ADNOC Secures Equity Position and LNG Offtake Agreement in NextDecades Rio Grande LNG Project] | ||
+ | # [https://lng-news.blogspot.com/2025/03/baker-hughes-nextdecade-enter-framework.html Baker Hughes, NextDecade Enter Framework Agreement for Rio Grande LNG Expansion Trains] | ||
[[category:LNG]] | [[category:LNG]] | ||
[[category:USA]] | [[category:USA]] |
Latest revision as of 15:03, 18 March 2025
Contents
Summary Information
- Ownership: NextDecade
- Website: http://next-decade.com/
- Location: Brownsville, Texas
- Capacity: 27.5 million tons/annum
- Status: Under construction
Brief Description
- The Rio Grande LNG project includes plans for up to six liquefaction trains, each with a nominal output capacity of 4.5 million tons of LNG per train per year
- Phase 1 includes the first 3 trains and FID was taken in 2023
- Phase 2 includes trains 4 & 5 and FID is expected in 2024
- Gas is to be supplied via the Rio Bravo Gas Pipeline from the Agua Dulce Natural Gas Hub
Technical Details
- Storage capacity: 4 x 180,000 m3 full containment LNG tanks
- Constructor:
- CB&I: Design and engineering activities required for the Federal Energy Regulatory Commission (FERC) permitting process, as well as for preparation for procurement of critical equipment prior to the final investment decision.
- Bechtel: Engineering, procurement, and construction (EPC)
- Baker Hughes: Supply of Main Refrigerant Compressors
- Licensor: Air Products
Ongoing Projects/Project Status
- Phase 1 commissioning is expected in 2026
Suppliers / Customers
- Suppliers:
- Customers:
- Galp - 1.0 mtpa
- Itochu - 1.0 mtpa
- Total - 5.4 mtpa
- ADNOC - 1.9mtpa from train 4
History
- 2015 - CB&I awarded FEED for permitting process
- 2015 - HOAs signed for 14 Mtpa of LNG
- 2019 - Bechtel awarded EPC contract
- 2021 - A Texas court orders the FERC to reassess the approval for the project
- 2022 - Galp signs an agreement to buy 1mtpa
- 2023 - Itochu signs an agreement to buy 1mtpa
- 2023 - Global Infrastructure Partners (GIP) and TotalEnergies agree to take stakes in phase 1
- 2023 - Final investment decision taken for phase 1
- 2024 - ADNOC announced the acquisition of a 11.7% stake in Phase 1 and a 1.9ntpa take off agreement
- 2025 - Baker Hughes awarded contract for gas turbine and refrigerant compressors for trains 4-8
Other Information
- -
Links
- Long Term Applications Received by DOE/FE
- Rio Grande LNG Submits Official Pre-File Request to the FERC and Receives Notification of Acceptance
- CB&I Announces Contract for Rio Grande LNG Project
- NextDecade Raises Additional $85 million in Pre-FID Funding for its Rio Grande LNG Project, Makes Significant Progress with FERC
- Appellate Court Remands Brownsville Channel LNG Orders to FERC
- Bechtel Awarded EPC Contract to Build Rio Grande LNG Project for NextDecade
- Galp enters into an agreement with NextDecade for U.S. LNG
- NextDecade and Itochu Corporation Execute 1.0 MTPA LNG Sale and Purchase Agreement
- NextDecade Announces Framework Agreements with Global Infrastructure Partners and TotalEnergies to Support the Development of the Rio Grande LNG Project
- Baker Hughes to Supply 3 Liquefaction Trains for NextDecade’s Rio Grande LNG Project
- NextDecade Announces Positive Final Investment Decision on Rio Grande LNG Phase 1
- Air Products’ LNG Liquefaction Technology and Equipment Selected for NextDecade’s Rio Grande LNG Project
- ADNOC Secures Equity Position and LNG Offtake Agreement in NextDecades Rio Grande LNG Project
- Baker Hughes, NextDecade Enter Framework Agreement for Rio Grande LNG Expansion Trains