Difference between revisions of "SK408 Block Gas and Condensate Fields"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
| (One intermediate revision by the same user not shown) | |||
| Line 11: | Line 11: | ||
=== Description === | === Description === | ||
* The project includes five natural gas and condensate fields, Gorek, Larak, Bakong, Teja, and Legundi. | * The project includes five natural gas and condensate fields, Gorek, Larak, Bakong, Teja, and Legundi. | ||
| + | * The Jerun platform is designed to produce up to 550 million cubic feet of gas per day, with condensate production of 15,000 barrels per day during peak production. | ||
* The gas is supplied to the [[Malaysia LNG Terminal]] | * The gas is supplied to the [[Malaysia LNG Terminal]] | ||
=== Contractors === | === Contractors === | ||
| − | * McDermott: | + | * '''McDermott:''' |
** Transportation and installation of jackets, topsides and pipelines for the Gorek gas field | ** Transportation and installation of jackets, topsides and pipelines for the Gorek gas field | ||
** Transportation and installation of jackets, topsides and pipelines for the Larak and Bakong gas fields. | ** Transportation and installation of jackets, topsides and pipelines for the Larak and Bakong gas fields. | ||
| Line 26: | Line 27: | ||
* 2020 - Gorek, Larak and Bakong came onstream | * 2020 - Gorek, Larak and Bakong came onstream | ||
* 2021 - FID for the Jerun field | * 2021 - FID for the Jerun field | ||
| + | * 2024 - First gas achieved at Jerun gas field | ||
=== Geology === | === Geology === | ||
| Line 34: | Line 36: | ||
# [https://abarrelfull.blogspot.com/2023/01/mcdermott-announces-contracts-for-pan.html McDermott Announces Contracts for Pan Malaysia Field Development] | # [https://abarrelfull.blogspot.com/2023/01/mcdermott-announces-contracts-for-pan.html McDermott Announces Contracts for Pan Malaysia Field Development] | ||
# [https://abarrelfull.blogspot.com/2023/01/sapuraomv-announces-bakong-first.html SapuraOMV announces Bakong first production from SK408 gas fields] | # [https://abarrelfull.blogspot.com/2023/01/sapuraomv-announces-bakong-first.html SapuraOMV announces Bakong first production from SK408 gas fields] | ||
| + | # [https://a-barrel-full.blogspot.com/2024/07/first-gas-achieved-at-jerun-gas-field.html First gas achieved at Jerun gas field in Malaysia] | ||
Latest revision as of 11:53, 15 July 2024
Summary Information
- Operator: SapuraOMV
- Country: Maslaysia
- Location: Offshore Sarawak
- Production start: 2019
- Partners: Shell, Petronas
- Type: Gas & Condensate
- Estimated Reserves:
- Production Volume:
Description
- The project includes five natural gas and condensate fields, Gorek, Larak, Bakong, Teja, and Legundi.
- The Jerun platform is designed to produce up to 550 million cubic feet of gas per day, with condensate production of 15,000 barrels per day during peak production.
- The gas is supplied to the Malaysia LNG Terminal
Contractors
- McDermott:
- Transportation and installation of jackets, topsides and pipelines for the Gorek gas field
- Transportation and installation of jackets, topsides and pipelines for the Larak and Bakong gas fields.
- Fabrication of risers and spools
History
- 2012 - Signed Production Sharing Contract for Block SK408 offshore
- 2014 - Gas discoveries at Bakong Teja, Gorek, Legundi & Larak prospects
- 2016 - Gas discoveries at Jerun & Jerimin
- 2019 - First Gas from Larak field
- 2020 - Gorek, Larak and Bakong came onstream
- 2021 - FID for the Jerun field
- 2024 - First gas achieved at Jerun gas field