Ownership: Exxon
+
* Ownership: Exxon
−
Website: http://www.exxonmobil.com/
+
* Website: http://www.exxonmobil.com/
−
List of Exxon Mobil Refineries
+
* List of Exxon Mobil Refineries
−
Wiki Page: [[Exxon Mobil Antwerp Refinery]]
+
* Wiki Page: [[Exxon Mobil Antwerp Refinery]]
−
Location: Antwerp, Belgium
+
* Location: Antwerp, Belgium
−
Capacity: 16 million tons/annum & 320,000 bbl/day
+
* Nelson Complexity:
−
Nelson Complexity:
+
* Project Stage: Completed
−
Project Stage: commissioning
+
* Expected Completion: 2018
−
Expected Completion: 2018
+
* Budget: $1 Billion
−
Budget:
+
=== The Project ===
−
The Project
+
* Project Type: Upgrade
−
Project Type: Upgrade
+
* Project Summary: Addition of a delayed coker unit to convert heavy, higher sulfur residual oils into transportation fuels products such as marine gasoil and diesel fuel
−
Project Summary: Addition of a delayed coker unit to convert heavy, higher sulfur residual oils into transportation fuels products such as marine gasoil and diesel fuel
+
=== Main Contractors: ===
−
Main Contractors:
+
* Foster Wheeler: Engineering, procurement, and construction (EPC)
−
Foster Wheeler: Engineering, procurement, and construction (EPC)
+
* Fluor: Design, engineering, procurement, module fabrication, transportation, installation and construction
−
Fluor: Design, engineering, procurement, module fabrication, transportation, installation and construction
+
=== Refining Units ===
−
Refining Units
+
* Delayed Coker: 50,000 bpd
−
Delayed Coker
+
 
−
Terminal Capacity
+
=== Terminal Capacity ===
−
Crude Oil:
+
* Crude Oil:
−
Refined Products:
+
* Refined Products:
−
Crude Supply
+
=== Crude Supply ===
−
No change
+
* No change
−
Products Produced
+
=== Products Produced ===
−
Decrease in residual products and an increase in middle distillates, particularly Diesel / Gasoil
+
* Decrease in residual products and an increase in middle distillates, particularly Diesel / Gasoil
−
History
+
 
−
2014 - Delayed Coker project announced
+
=== History ===
−
2014 - Construction started
+
* 2014 - Delayed Coker project announced
−
Other Information
+
* 2014 - Construction started
 +
* 2018 - Project completed
 +
=== Other Information ===
 
-
 
-
−
Relevant Links
+
=== Links ===
−
ExxonMobil Announces Antwerp Refinery Investment of More Than $1 Billion
+
# [http://killajoules.wikidot.com/blog:5284 ExxonMobil Announces Antwerp Refinery Investment of More Than $1 Billion]
−
Foster Wheeler Awarded EPC Contract For ExxonMobil’s Antwerp Refinery Upgrade In Belgium
+
# [http://killajoules.wikidot.com/blog:5514 Foster Wheeler Awarded EPC Contract For ExxonMobil’s Antwerp Refinery Upgrade In Belgium]
−
Fluor Begins Work on ExxonMobil Antwerp Refinery Delayed Coker Project in Belgium
+
# [http://killajoules.wikidot.com/blog:5650 Fluor Begins Work on ExxonMobil Antwerp Refinery Delayed Coker Project in Belgium]
−
Construction coker unit almost completed
+
# [http://killajoules.wikidot.com/blog:5284 ExxonMobil Announces Antwerp Refinery Investment of More Than $1 Billion]
 +
# [http://killajoules.wikidot.com/archive:exxonmobil-starts-new-unit-at-antwerp-refinery-to-pr ExxonMobil Starts New Unit at Antwerp Refinery to Produce High-Value Transportation Fuels]
 +
 
 +
[[category:Refinery]]
 +
[[category:Project]]
 +
[[category:Exxon]]
 +
[[category:Belgium]]

Latest revision as of 18:04, 8 February 2020

Summary Information

The Project

  • Project Type: Upgrade
  • Project Summary: Addition of a delayed coker unit to convert heavy, higher sulfur residual oils into transportation fuels products such as marine gasoil and diesel fuel

Main Contractors:

  • Foster Wheeler: Engineering, procurement, and construction (EPC)
  • Fluor: Design, engineering, procurement, module fabrication, transportation, installation and construction

Refining Units

  • Delayed Coker: 50,000 bpd

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • No change

Products Produced

  • Decrease in residual products and an increase in middle distillates, particularly Diesel / Gasoil

History

  • 2014 - Delayed Coker project announced
  • 2014 - Construction started
  • 2018 - Project completed

Other Information

-

Links

  1. ExxonMobil Announces Antwerp Refinery Investment of More Than $1 Billion
  2. Foster Wheeler Awarded EPC Contract For ExxonMobil’s Antwerp Refinery Upgrade In Belgium
  3. Fluor Begins Work on ExxonMobil Antwerp Refinery Delayed Coker Project in Belgium
  4. ExxonMobil Announces Antwerp Refinery Investment of More Than $1 Billion
  5. ExxonMobil Starts New Unit at Antwerp Refinery to Produce High-Value Transportation Fuels