=== Pipeline Status ===
 
=== Pipeline Status ===
* Planning
+
* Cancelled
 
*  Subject to customer commitments and regulatory approval, the Westward Ho Pipeline is expected to begin service by early 2015
 
*  Subject to customer commitments and regulatory approval, the Westward Ho Pipeline is expected to begin service by early 2015
  
Line 20: Line 20:
 
* 2011 - non-binding solicitation of interest period  
 
* 2011 - non-binding solicitation of interest period  
 
* 2012 - Shell successfully concluded its binding Open Season period for firm capacity
 
* 2012 - Shell successfully concluded its binding Open Season period for firm capacity
 +
* 2015 - The project was canacelled
  
 
=== Other Information ===
 
=== Other Information ===

Latest revision as of 17:02, 14 July 2024

Summary Information

  • Source: St. James, LA, USA
  • Destination: Port Neches/Nederland, TX, USA
  • Ownership: Shell
  • Website: http://www.shell.us/
  • Length: kilometres ( miles)
  • Capacity: 600,000 barrels of oil per day
  • Crude Type: domestic production and foreign crude available at St. James, LA.

The Route

  • St. James, LA to the Port Neches/Nederland, TX

Pipeline Status

  • Cancelled
  • Subject to customer commitments and regulatory approval, the Westward Ho Pipeline is expected to begin service by early 2015

History

  • 2011 - non-binding solicitation of interest period
  • 2012 - Shell successfully concluded its binding Open Season period for firm capacity
  • 2015 - The project was canacelled

Other Information

  • -