(Created page with "=== Summary Information === * Ownership: PTT LNG * Website: http://www.pttlng.com/ * Location: Map Ta Phut Thailand * Capacity: 5.0 million tons/annum * Status: In operatio...")
 
 
(4 intermediate revisions by the same user not shown)
Line 7: Line 7:
 
* Status: In operation
 
* Status: In operation
  
+++ Brief Description
+
=== Brief Description ===
 
* A large single train LNG gasification terminal
 
* A large single train LNG gasification terminal
  
+++ Technical Details
+
=== Technical Details ===
 
* Storage capacity: 160,000 m3 x 2
 
* Storage capacity: 160,000 m3 x 2
 
* Unloading capacity: LNG vessels size with 125,000 to 264,000 cubic meters capacity
 
* Unloading capacity: LNG vessels size with 125,000 to 264,000 cubic meters capacity
 
* Send out capacity: 700 mmscfd
 
* Send out capacity: 700 mmscfd
 
* Constructor:  
 
* Constructor:  
* **Fluor:** Project Management and Consultant role
+
** **Fluor:** Project Management and Consultant role
* **GS/Kogas/HYC/DEC:** Integrated engineering, procurement, construction and commissioning services of a re-gasification and send-out system, a marine jetty with complete ship unloading facilities and two large full containment LNG storage tanks.
+
** **GS/Kogas/HYC/DEC:** Integrated engineering, procurement, construction and commissioning services of a re-gasification and send-out system, a marine jetty with complete ship unloading facilities and two large full containment LNG storage tanks.
* **Freyssinet:** Pre-stressing for LNG tanks  
+
** **Freyssinet:** Pre-stressing for LNG tanks
  
 
+
=== Ongoing Projects/Project Status ===
+++ Ongoing Projects/Project Status
+
* Project was completed in [[LNG Terminal Projects Completed in 2011 | 2011]]
* Project was completed in [[[LNG Terminals to be Completed in 2011 | 2011]]]
 
 
* PTT is planning to double the capacity of the terminal
 
* PTT is planning to double the capacity of the terminal
  
  
+++ Suppliers / Customers
+
=== Suppliers / Customers ===
 
* Suppliers:  
 
* Suppliers:  
* PTT has signed a deal to buy 1 million tonnes of LNG a year from Qatar from late 2011
+
** PTT has signed a deal to buy 1 million tonnes of LNG a year from Qatar from late 2011
* PTT also plans to buy LNG in spot markets in 2011-2014 if market conditions are favourable
+
** PTT also buys LNG in spot markets  
* Customers: The area has petrochemical, refinery, steel and fertiliser industries  
+
* Customers: The area has petrochemical, refinery, steel and fertiliser industries
  
 
+
=== History ===
+++ History
 
 
* 2006 - Fluor awarded Project Management and Consultant role
 
* 2006 - Fluor awarded Project Management and Consultant role
 
* 2008 - Consortium of GS/Kogas/HYC/DEC awarded construction contract  
 
* 2008 - Consortium of GS/Kogas/HYC/DEC awarded construction contract  
Line 38: Line 36:
 
* 2011 - Terminal opening
 
* 2011 - Terminal opening
 
* 2012 - PTT – Qatargas sign 20-year LNG supply agreement
 
* 2012 - PTT – Qatargas sign 20-year LNG supply agreement
 +
* 2017 - Terminal expansion project completed
  
+++ Other Information
+
=== Other Information ===
 
* This construction of LNG receiving terminal in Thailand is the first overseas LNG terminal project as Korean E&C companies.
 
* This construction of LNG receiving terminal in Thailand is the first overseas LNG terminal project as Korean E&C companies.
  
Line 53: Line 52:
 
# [http://www.bangkokpost.com/business/economics/255518/400m-lng-expansion $400m LNG expansion]
 
# [http://www.bangkokpost.com/business/economics/255518/400m-lng-expansion $400m LNG expansion]
 
# [http://killajoules.wikidot.com/blog:3548 PTT – Qatargas sign 20-year LNG supply agreement for energy reserve, greater national energy security with a supply start-up planned for early 2015]
 
# [http://killajoules.wikidot.com/blog:3548 PTT – Qatargas sign 20-year LNG supply agreement for energy reserve, greater national energy security with a supply start-up planned for early 2015]
 +
 +
[[category:LNG]]
 +
[[category:Thailand]]
 +
[[category:PTT]]

Latest revision as of 09:14, 15 May 2024

Summary Information

  • Ownership: PTT LNG
  • Website: http://www.pttlng.com/
  • Location: Map Ta Phut Thailand
  • Capacity: 5.0 million tons/annum
  • Status: In operation

Brief Description

  • A large single train LNG gasification terminal

Technical Details

  • Storage capacity: 160,000 m3 x 2
  • Unloading capacity: LNG vessels size with 125,000 to 264,000 cubic meters capacity
  • Send out capacity: 700 mmscfd
  • Constructor:
    • **Fluor:** Project Management and Consultant role
    • **GS/Kogas/HYC/DEC:** Integrated engineering, procurement, construction and commissioning services of a re-gasification and send-out system, a marine jetty with complete ship unloading facilities and two large full containment LNG storage tanks.
    • **Freyssinet:** Pre-stressing for LNG tanks

Ongoing Projects/Project Status

  • Project was completed in 2011
  • PTT is planning to double the capacity of the terminal


Suppliers / Customers

  • Suppliers:
    • PTT has signed a deal to buy 1 million tonnes of LNG a year from Qatar from late 2011
    • PTT also buys LNG in spot markets
  • Customers: The area has petrochemical, refinery, steel and fertiliser industries

History

  • 2006 - Fluor awarded Project Management and Consultant role
  • 2008 - Consortium of GS/Kogas/HYC/DEC awarded construction contract
  • 2011 - The terminal receives its first cargo
  • 2011 - Terminal opening
  • 2012 - PTT – Qatargas sign 20-year LNG supply agreement
  • 2017 - Terminal expansion project completed

Other Information

  • This construction of LNG receiving terminal in Thailand is the first overseas LNG terminal project as Korean E&C companies.

Links

  1. Freyssinet LNG Tank References
  2. 540 USD mil Overseas LNG Terminal Plant Award
  3. Thailand LNG Project Development and Outlook
  4. GS E&C-Led Team wins the first LNG Re-gasification Terminal Contract in Thailand
  5. Thailand's first LNG terminal to operate from July-PTT
  6. QATARGAS COMMISSIONS THAILAND’S FIRST LNG RECEIVING TERMINAL
  7. Thailand Minister of Energy inaugurates sixth gas separation plant and LNG terminal
  8. $400m LNG expansion
  9. PTT – Qatargas sign 20-year LNG supply agreement for energy reserve, greater national energy security with a supply start-up planned for early 2015