| − | * | + | * 2013 - First gas was produced |
| + | * 2018 - Phase 2 began production | ||
=== Geology === | === Geology === | ||
Latest revision as of 14:22, 1 December 2023
Summary Information
- Operator: Perenco
- Country: Cameroon
- Location:
- Production start:
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- The gas field is located 10 km offshore, north-west of Kribi, Cameroon.
- The field uses the Sanaga 01 Mobile Offshore Production Unit (MOPU) and an onshore gas processing plant. Liquids are supplied to the Ebomé storage platform
- The field was developed to supplied the Kribi gas fired power plant.
- The second phase of the project involves the Cameroon Hilli FLNG Terminal
Contractors
- Overdick: Engineering, design and installation of the Sanaga 1 MOPU
History
- 2013 - First gas was produced
- 2018 - Phase 2 began production