Line 20: Line 20:
 
#* Scope of work: Project management, Basic engineering, Detailed engineering, Procurement, Site and construction supervision, Commissioning assistance
 
#* Scope of work: Project management, Basic engineering, Detailed engineering, Procurement, Site and construction supervision, Commissioning assistance
 
#* Commissioning: 2014
 
#* Commissioning: 2014
 +
# [[Schwechat Refinery]]
 +
#* butadiene production unit
 +
#* EPCM-Contractor for capacity extensions to Butadiene production unit
 +
#* Client: OMV AG
 +
#* Location: Schwechat / Austria
 +
#* Scope of work:
 +
#** Project management, Basic engineering, Detailed engineering, Procurement, Site and construction supervision, Commissioning assistance,
 +
#* Commissioning: 2014
 +
# [[Schwedt Refinery]]
 +
#* revamp vacuum plant
 +
#* Exchange of the vacuum column of the vacuum plant based on the modern deep-cut process
 +
#* Client: PCK Raffinerie GmbH Schwedt
 +
#* Location: Schwedt / Germany
 +
#* Scope of work: Basic engineering, Detailed engineering, Procurement, Construction and installation supervision, Commissioning support
 +
#* Commissioning: 2013
  
butadiene production unit
 
 
EPCM-Contractor for capacity extensions to Butadiene production unit
 
Client: OMV AG
 
Location: Schwechat / Austria
 
Scope of work:
 
Project management
 
Basic engineering
 
Detailed engineering
 
Procurement
 
Site and construction supervision
 
Commissioning assistance
 
Commissioning: 2014
 
revamp vacuum plant
 
 
Exchange of the vacuum column of the vacuum plant based on the modern deep-cut process
 
Client: PCK Raffinerie GmbH Schwedt
 
Location: Schwedt / Germany
 
Scope of work:
 
Basic engineering
 
Detailed engineering
 
Procurement
 
Construction and installation supervision
 
Commissioning support
 
Commissioning: 2013
 
 
propane deasphalting plant (pda)
 
propane deasphalting plant (pda)
  

Revision as of 16:57, 19 November 2023

  1. Schwedt Refinery
    • Desulphurization plant - hazop findings dk2
    • Revamp of medium-pressure desulphurization plant DK2 with replacement of stripping column including foundation
    • Client: PCK Raffinerie GmbH Schwedt
    • Location: Schwedt, Germany
    • Scope of work: Basic engineering, Detail engineering, Procurement, Construction supervision
    • Commissioning: 2014
  2. Buna SOW Leuna Refinery
    • alkylation plant
    • Revamp of alkylation plant to increase alkylate yield
    • Client: TOTAL Raffinerie Mitteldeutschland GmbH
    • Location: Leuna, Germany
    • Scope of work: Detail engineering, Procurement, Construction supervision, Commissioning
    • Commissioning: 2014
  3. Schwechat Refinery
    • rd4 program
    • EPCM-Contractor for modernization of the crude oil distillation plant4 (RD4), distillation plant1 (DEA1), distillation plant2 (DEA2), new residue cooling system (RSK) to increase cooling capacity at residue line
    • Client: OMV AG
    • Location: Schwechat / Austria
    • Scope of work: Project management, Basic engineering, Detailed engineering, Procurement, Site and construction supervision, Commissioning assistance
    • Commissioning: 2014
  4. Schwechat Refinery
    • butadiene production unit
    • EPCM-Contractor for capacity extensions to Butadiene production unit
    • Client: OMV AG
    • Location: Schwechat / Austria
    • Scope of work:
      • Project management, Basic engineering, Detailed engineering, Procurement, Site and construction supervision, Commissioning assistance,
    • Commissioning: 2014
  5. Schwedt Refinery
    • revamp vacuum plant
    • Exchange of the vacuum column of the vacuum plant based on the modern deep-cut process
    • Client: PCK Raffinerie GmbH Schwedt
    • Location: Schwedt / Germany
    • Scope of work: Basic engineering, Detailed engineering, Procurement, Construction and installation supervision, Commissioning support
    • Commissioning: 2013

propane deasphalting plant (pda)

The new PDA plant is to obtain deasphalted oil from vacuum residue by propane extraction. Client: H&R Ölwerke Schindler GmbH Location: Hamburg / Germany Scope of work: Basic engineering Detailed engineering Procurement Construction supervision Commissioning Commissioning: 2011 crude oil distillation plant 4 schwechat

EPCM-Contractor for modernizing the crude oil distillation plant 4 (RD4) in Schwechat including the modernization of the lower circulation return lines of the distillation plant Client: OMV Location: Schwechat / Austria Scope of work: Detailed engineering Procurement and expediting Construction and installation supervision Commissioning Commissioning: 2010 revamp crude oil distillation plant top1

Replacement of the main column for improvement of MD recovery and for production of a jet fuel component; replacement of column with a 1350t crane and assembly of column parts on site Client: PCK Raffinerie Schwedt Location: Schwedt / Germany Scope of work: Detailed engineering Construction and installation supervision Procurement Expediting Commissioning: 2010 revamp fcc gas concentration plant

Revamp of the stripping column with further peripheral equipment to improve the propene recovery process Client: PCK Raffinerie GmbH Schwedt Location: Schwedt / Germany Scope of work: Basic engineering Detailed engineering Procurement and expediting Construction and installation supervision Commissioning Commissioning: 2010 revamp of hds plant

Complete revamp of the desulfurization plant HDS-1 in Schwechat to reduce the sulfur production to less than 10ppm and triple the capacity from 1000 t/d to 3500 t/d by EDL Client: OMV AG Location: Schwechat, Austria Scope of work: Project management Detailed engineering Procurement Construction supervision Commissioning Commissioning: 2008 used oil re- refining plant

Planning and erection of a new used oil re-refining plant (Hylube2) based on UOP technology Client: Puralube Raffinerie GmbH Location: Zeitz, Germany Scope of work: Basic engineering Detailed engineering Procurement support Commissioning support Commissioning: 2008

fcc-overcracking-plant

FCC overcracking plant with C3 splitter process stage as the core part of the plant (diameter 5.2 m, total height 84 m) to produce propylene in polymer grade quality Client: PCK Raffinerie GmbH, Schwedt Location: Schwedt, Germany Scope of work: Detailed engineering Procurement Construction supervision Commissioning: 2007 Investment: EUR 29 million (in total) debottlenecking of refinery gas plant

Debottlenecking of refinery gas plant Client: OMV Deutschland GmbH Location: Burghausen, Germany Scope of work: Detailed engineering Procurement Construction supervision Site management Commissioning: 2007 revamp hf alkylation

Revamp of existing HF alkylation Client: PCK Raffinerie GmbH, Schwedt Location: Schwedt, Germany Scope of work: Basic engineering (UOP Schedule A) Detailed engineering Procurement Construction supervision Commissioning: 2007 ok 95 - transfer line

Transfer line OK 95 (with/without ETBE) Client: TOTAL Raffinerie Mitteldeutschland GmbH Location: Leuna, Germany Scope of work: Detailed engineering Procurement Construction supervision Commissioning: 2006 revamp of hds-1 plant

Revamp of HDS-1 plant Client: OMV Deutschland GmbH Location: Burghausen, Germany Scope of work: Detailed engineering Procurement Construction supervision Commissioning 2006 new refinery gas plant

New refinery gas plant Modification of associated existing units Client: BAYERNOIL Raffineriegesellschaft LocationIngolstadt, Germany Scope of work: Detailed engineering Procurement (support) Authority engineering Investment cost estimate Construction supervision (piping) Acceptance tests/Tests Start-up assistance Commissioning: 2005

revamp of coking plant Project: Revamp of coking plant with capacity increase Client: BP Erdöl-Raffinerie-Emsland Location: Lingen, Germany Scope of work: Detailed engineering Procurement Construction supervision Commissioning: 2004 fcc column

Replacement of existing FCC main column by a larger (diameter of 6.2 m) and higher (height of 54 m) one Client: Raffinerie GmbH, Schwedt Location: Schwedt, Germany Scope of work: Basic engineering Detailed engineering Procurement Construction supervision Acceptance tests/Tests Start-up assistance Commissioning: 2004 revamp of light gasoline isomerization

Revamp of UOP reformer for isomerization of light gasoline based on UOP-Par Isom technology and a UOP reactor design package Location: Lingen, Germany Scope of work: Extended basic engineering Authority engineering Investment cost estimate Procurement support Detailed engineering Commissioning: 2002 desulphurization unit Desus 2

Project: Increase of throughput of desulphurization unit DESUS 2 to 140 tph Client: PCK Raffinerie GmbH Location: Schwedt, Germany Scope of work: Basic engineering Detailed engineering Procurement Construction supervision Start-up assistance Commissioning: 2002