Difference between revisions of "Santa Catarina LNG Terminal"

From A Barrel Full
Jump to navigation Jump to search
Line 37: Line 37:
 
=== Links ===
 
=== Links ===
 
# [https://www.newfortressenergy.com/stories/santa-catarina-terminal-page Terminal Page, New Fortress Energy]
 
# [https://www.newfortressenergy.com/stories/santa-catarina-terminal-page Terminal Page, New Fortress Energy]
https://abarrelfull.blogspot.com/2023/11/tenenge-starts-construction-of-gas.html Tenenge starts construction of Gas Terminal in Santa Catarina]
+
# [https://abarrelfull.blogspot.com/2023/11/tenenge-starts-construction-of-gas.html Tenenge starts construction of Gas Terminal in Santa Catarina]
 
# [https://lng-news.blogspot.com/2023/11/new-fortress-energy-signs-fsru-charter.html New Fortress Energy Signs FSRU Charter to Start Operations of LNG Import Terminal in Santa Catarina, Brazil in January 2024]
 
# [https://lng-news.blogspot.com/2023/11/new-fortress-energy-signs-fsru-charter.html New Fortress Energy Signs FSRU Charter to Start Operations of LNG Import Terminal in Santa Catarina, Brazil in January 2024]
  

Revision as of 13:19, 6 November 2023

Summary Information

Brief Description

  • The terminal utilises the Floating Storage and Regasification Unit (“FSRU”) Energos Winter which has the capacity to store 160,000 cubic meters of LNG.
  • The TGS will be located 300 meters from the coast.
  • After regasification, the natural gas continues for about 2 kilometers in a pipeline under the bed of the bay, until it flows into the same entry point of the OSPAR pipeline, in Itapoá

Technical Details

  • Storage capacity: 160,000 cubic meters
  • Unloading capacity:
  • Send out capacity:
  • Constructor: Tenenge built the connections to the local grid

Ongoing Projects/Project Status

  • The terminal is scheduled to start operations in January 2024.

Suppliers / Customers

  • Suppliers:
  • Customers:

History

  • 2021 - Construction was started
  • 2023 - Charter signed for FSRU vessel

Other Information

-

Links

  1. Terminal Page, New Fortress Energy
  2. Tenenge starts construction of Gas Terminal in Santa Catarina
  3. New Fortress Energy Signs FSRU Charter to Start Operations of LNG Import Terminal in Santa Catarina, Brazil in January 2024