Difference between revisions of "North Malay Basin Gas Fields"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 16: | Line 16: | ||
* Phase 2 of the Field Development Plan (FDP) developed the Zetung and Anggerik fields with nine production wells and the construction, transport and installation of two three-legged remote wellhead platforms, as well as the pipelines that serves them, with gas flowing to the CPP. | * Phase 2 of the Field Development Plan (FDP) developed the Zetung and Anggerik fields with nine production wells and the construction, transport and installation of two three-legged remote wellhead platforms, as well as the pipelines that serves them, with gas flowing to the CPP. | ||
* The NMB Phase 3 project includes the installation of the new Bergading-B Wellhead Platform that adds another 100 million cubic feet per day (MMscfd) of gas supply from Block PM302, bringing the total production to 400 MMscfd. | * The NMB Phase 3 project includes the installation of the new Bergading-B Wellhead Platform that adds another 100 million cubic feet per day (MMscfd) of gas supply from Block PM302, bringing the total production to 400 MMscfd. | ||
+ | * A fourth phase is under development will accommodate the Dahlia, Kangsar and Teratai fields in the eastern part of NMB and include the fabrication and installation of one remote and two minimal wellhead platforms connected back to the CPP. | ||
=== Contractors === | === Contractors === | ||
Line 36: | Line 37: | ||
# [https://abarrelfull.blogspot.com/2023/10/north-malay-basin-phase-3-block-pm302.html North Malay Basin Phase 3 Block PM302 Achieves First Gas Production] | # [https://abarrelfull.blogspot.com/2023/10/north-malay-basin-phase-3-block-pm302.html North Malay Basin Phase 3 Block PM302 Achieves First Gas Production] | ||
# [https://a-barrel-full.blogspot.com/2023/10/chevron-announces-agreement-to-acquire.html Chevron announces agreement to acquire Hess] | # [https://a-barrel-full.blogspot.com/2023/10/chevron-announces-agreement-to-acquire.html Chevron announces agreement to acquire Hess] | ||
+ | # [https://abarrelfull.blogspot.com/2023/10/unlocking-value-new-resources-in-gulf.html Unlocking Value & New Resources in the Gulf of Thailand] | ||
[[category:Field]] | [[category:Field]] |
Revision as of 06:02, 24 October 2023
Summary Information
- Operator: Hess
- Country: Malaysia
- Location: PM302, PM325 and PM326B
- Production start:
- Partners: Petronas / Hess
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- The initial development concept for NMB targeted nine stranded gas fields – Bergading, Bunga Dahlia, Teratai, Gajah, Melati, Kamelia, Zetung, Anggerik and Kesumba through the deployment of a floating production storage and offloading (FPSO) vessel. Later in 2018, a tenth field was identified, Bunga Kangsar.
- A 300-kilometers offshore pipeline connects production to the Terengganu Gas Terminal (TGAST) plant
- The early production system (EPS) included just the Kamelia field and used a wellhead platform and the leased floating production, storage and offloading vessel Perisai Kamelia FPSO
- Phase 1 of the Field Development Plan (FDP) included the Bergading central processing platform (CPP) that bridge-linked to Bergading A wellhead platform, and three additional wellhead platforms – the Bergading C, Bergading D and Kesumba platforms.
- Phase 2 of the Field Development Plan (FDP) developed the Zetung and Anggerik fields with nine production wells and the construction, transport and installation of two three-legged remote wellhead platforms, as well as the pipelines that serves them, with gas flowing to the CPP.
- The NMB Phase 3 project includes the installation of the new Bergading-B Wellhead Platform that adds another 100 million cubic feet per day (MMscfd) of gas supply from Block PM302, bringing the total production to 400 MMscfd.
- A fourth phase is under development will accommodate the Dahlia, Kangsar and Teratai fields in the eastern part of NMB and include the fabrication and installation of one remote and two minimal wellhead platforms connected back to the CPP.
Contractors
- -
History
- 2012 - Hess and Petronas sign agreement to develop the basin
- 2013 - First gas from the early production system (EPS)
- 2017 - First gas from phase 1 and TGAST completed
- 2019 - First gas from phase 2
- 2019 - FID for Phase 3
- 2022 - First oil from phase 3 development
- 2023 - Chevron agreed to acquire Hess, becoming a partner