Difference between revisions of "Dhamra LNG Terminal"
		
		
		
		
		Jump to navigation
		Jump to search
		
Abarrelfull (talk | contribs)  | 
				Abarrelfull (talk | contribs)   | 
				||
| (19 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
=== Summary Information ===  | === Summary Information ===  | ||
| − | * Ownership:   | + | * Ownership: Total Energies / Adani  | 
* Website: http://www.dhamraport.com/  | * Website: http://www.dhamraport.com/  | ||
* Location: Dhamra, India  | * Location: Dhamra, India  | ||
* Capacity: 5 million tons/annum    | * Capacity: 5 million tons/annum    | ||
| − | * Status:   | + | * Status: In operation  | 
=== Brief Description ===  | === Brief Description ===  | ||
| − | *   | + | * The Dhamra LNG import terminal is designed for an initial capacity of 5 MTPA, expandable up to 10 MTPA. Initially, it will have two full containment type tanks of 180,000 m3 capacity each.  | 
=== Technical Details ===  | === Technical Details ===  | ||
| − | * Storage capacity:  | + | * Storage capacity: Two full containment type tanks of 170,000 m3  | 
| − | * Unloading capacity:  | + | * Unloading capacity: It will have a jetty capable of handling a wide range of LNG supply vessels, including the largest Q-max fleet  | 
* Send out capacity:    | * Send out capacity:    | ||
* Constructor:  | * Constructor:  | ||
| − | *   | + | ** Larsen and Toubro: Construction of the tanks  | 
| − | + | ** Whessoe Engineering: Detailed Engineering & Construction Supervision for the tanks  | |
| + | ** CTCI: Regas Package  | ||
=== Ongoing Projects/Project Status ===  | === Ongoing Projects/Project Status ===  | ||
| − | *   | + | * The terminal was completed in [[LNG Terminal Projects to be Completed in 2023 | 2023]]  | 
=== Suppliers / Customers ===  | === Suppliers / Customers ===  | ||
* Suppliers:    | * Suppliers:    | ||
| − | * Customers: IOCL refineries at Paradip (in Orissa) and Haldia (in West Bengal) need 2.5 million tons of LNG  | + | * Customers:    | 
| − | + | ** IOCL refineries at Paradip (in Orissa) and Haldia (in West Bengal) need 2.5 million tons of LNG  | |
| + | ** GAIL India has booked 1.5 million tonnes per annum (MTPA) regasification capacity for a period of 20 years.  | ||
=== History ===  | === History ===  | ||
| − | * -    | + | * 2017 - Construction started  | 
| + | * 2018 - CTCI awarded regasification package  | ||
| + | * 2018 - Gail and IOCL sign contracts for 4.5 mn tons per annum  | ||
| + | * 2023 - First cargo delivered  | ||
=== Other Information ===  | === Other Information ===  | ||
| Line 33: | Line 38: | ||
=== Links ===  | === Links ===  | ||
| + | # [[Whessoe Engineering LNG References]]  | ||
# [http://www.livemint.com/2011/06/12230522/East-coast-to-get-first-LNG-im.html?atype=tp East coast to get first LNG import terminal]  | # [http://www.livemint.com/2011/06/12230522/East-coast-to-get-first-LNG-im.html?atype=tp East coast to get first LNG import terminal]  | ||
| − | # [  | + | # [https://abarrelfull.blogspot.com/2021/12/adani-ports-signs-long-term_30.html Adani Ports signs a long term regasification pact with Indian Oil for Dhamra LNG terminal]  | 
# [http://killajoules.wikidot.com/archive:indianoil-and-gail-sign-mou-for-taking-equity-stake IndianOil and GAIL sign MoU for taking equity stake in upcoming Dhamra LNG terminal]  | # [http://killajoules.wikidot.com/archive:indianoil-and-gail-sign-mou-for-taking-equity-stake IndianOil and GAIL sign MoU for taking equity stake in upcoming Dhamra LNG terminal]  | ||
| + | # [https://abarrelfull.blogspot.com/2021/12/ctci-wins-regas-package-for-lng.html CTCI Wins Regas Package for LNG Receiving Terminal Project at Dhamra Odisha from Adani Group]  | ||
| + | # [https://abarrelfull.blogspot.com/2021/12/adani-ports-signs-long-term.html Adani Ports signs a long term regasification pact with GAIL India Ltd for Dhamra LNG terminal]  | ||
| + | # [https://lng-news.blogspot.com/2023/04/qatargas-supplies-commissioning-lng.html Qatargas Supplies Commissioning LNG Cargo To India’s Dhamra Terminal]  | ||
| + | |||
| + | [[Category:LNG]]  | ||
| + | [[Category:India]]  | ||
| + | [[Category:Total]]  | ||
Latest revision as of 15:05, 17 April 2023
Contents
Summary Information
- Ownership: Total Energies / Adani
 - Website: http://www.dhamraport.com/
 - Location: Dhamra, India
 - Capacity: 5 million tons/annum
 - Status: In operation
 
Brief Description
- The Dhamra LNG import terminal is designed for an initial capacity of 5 MTPA, expandable up to 10 MTPA. Initially, it will have two full containment type tanks of 180,000 m3 capacity each.
 
Technical Details
- Storage capacity: Two full containment type tanks of 170,000 m3
 - Unloading capacity: It will have a jetty capable of handling a wide range of LNG supply vessels, including the largest Q-max fleet
 - Send out capacity:
 - Constructor:
- Larsen and Toubro: Construction of the tanks
 - Whessoe Engineering: Detailed Engineering & Construction Supervision for the tanks
 - CTCI: Regas Package
 
 
Ongoing Projects/Project Status
- The terminal was completed in 2023
 
Suppliers / Customers
- Suppliers:
 - Customers:
- IOCL refineries at Paradip (in Orissa) and Haldia (in West Bengal) need 2.5 million tons of LNG
 - GAIL India has booked 1.5 million tonnes per annum (MTPA) regasification capacity for a period of 20 years.
 
 
History
- 2017 - Construction started
 - 2018 - CTCI awarded regasification package
 - 2018 - Gail and IOCL sign contracts for 4.5 mn tons per annum
 - 2023 - First cargo delivered
 
Other Information
- -
 
Links
- Whessoe Engineering LNG References
 - East coast to get first LNG import terminal
 - Adani Ports signs a long term regasification pact with Indian Oil for Dhamra LNG terminal
 - IndianOil and GAIL sign MoU for taking equity stake in upcoming Dhamra LNG terminal
 - CTCI Wins Regas Package for LNG Receiving Terminal Project at Dhamra Odisha from Adani Group
 - Adani Ports signs a long term regasification pact with GAIL India Ltd for Dhamra LNG terminal
 - Qatargas Supplies Commissioning LNG Cargo To India’s Dhamra Terminal