Difference between revisions of "Prosperity FPSO"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 16: | Line 16: | ||
=== Contractors === | === Contractors === | ||
* SBM Offshore was awarded the contract to construct, install and then lease and operate the vessel | * SBM Offshore was awarded the contract to construct, install and then lease and operate the vessel | ||
+ | * Keppel O&M: Fabrication of several topside modules, riser, mooring and umbilical structures, followed by the installation and integration of these structures and all topside modules onto the FPSO. | ||
=== Status === | === Status === | ||
Line 23: | Line 24: | ||
* 2020 - SBM Offshore awarded the contract to supply the FPSO | * 2020 - SBM Offshore awarded the contract to supply the FPSO | ||
* 2021 - The hull arrived in the Keppel yard in Singapore for topsides integration | * 2021 - The hull arrived in the Keppel yard in Singapore for topsides integration | ||
+ | * 2023 - The FPSO was completed | ||
=== Other Information === | === Other Information === | ||
Line 31: | Line 33: | ||
# [https://abarrelfull.blogspot.com/2021/11/sbm-offshore-awarded-contracts-for.html SBM Offshore awarded contracts for ExxonMobil FPSO Prosperity] | # [https://abarrelfull.blogspot.com/2021/11/sbm-offshore-awarded-contracts-for.html SBM Offshore awarded contracts for ExxonMobil FPSO Prosperity] | ||
# [https://abarrelfull.blogspot.com/2021/11/prosperity-fpso-hull-arrives-in.html Prosperity FPSO hull arrives in Singapore for next phase of construction] | # [https://abarrelfull.blogspot.com/2021/11/prosperity-fpso-hull-arrives-in.html Prosperity FPSO hull arrives in Singapore for next phase of construction] | ||
+ | # [https://a-barrel-full.blogspot.com/2023/03/keppel-o-to-deliver-guyanas-third-fpso.html Keppel O&M to deliver Guyana's third FPSO] |
Revision as of 15:50, 5 March 2023
Contents
Summary Information
- Name: Prosperity FPSO
- Field: Payara Oil Field
- Country: Guyana
- Ownership: SBM Offshore
- Website: https://www.sbmoffshore.com/
- Field Operated By: Exxon
- Capacity: 220,000 bpd
- Year of Completion: 2024 (expected)
Brief Description
- The vessel is intended to produce roughly 220,000 barrels of oil per day, will have associated gas treatment capacity of 400 million cubic feet per day and water injection capacity of 250,000 barrels per day. and will be able to store around 2 million barrels of crude oil
Contractors
- SBM Offshore was awarded the contract to construct, install and then lease and operate the vessel
- Keppel O&M: Fabrication of several topside modules, riser, mooring and umbilical structures, followed by the installation and integration of these structures and all topside modules onto the FPSO.
Status
- Under construction
History
- 2020 - SBM Offshore awarded the contract to supply the FPSO
- 2021 - The hull arrived in the Keppel yard in Singapore for topsides integration
- 2023 - The FPSO was completed
Other Information
- -