=== Summary Information ===
 
=== Summary Information ===
  
Operator: Statoil
+
* Operator: Equinor
Country: Norway
+
* Country: Norway
Location: Tampen area in the northern part of the North Sea
+
* Location: Tampen area in the northern part of the North Sea
Production start: 1992
+
* Production start: 1992
Partners: Statoil - 33.28%, Petoro - 30.0%, ExxonMobil - 17.45%, Idemitsu - 9.6%, RWE Dea - 8.57% and Core Energy 1.11%
+
* Partners: Statoil - 33.28%, Petoro - 30.0%, ExxonMobil - 17.45%, Idemitsu - 9.6%, RWE Dea - 8.57% and Core Energy 1.11%
Type: Oil
+
* Type: Oil
Estimated Reserves: Original
+
* Estimated Reserves: Original
249.9 million Sm³ oil
+
** 249.9 million Sm³ oil
6.6 billion Sm³ gas
+
** 6.6 billion Sm³ gas
4.7 million tonnes NGL
+
** 4.7 million tonnes NGL
Production Volume: 85 000 barrels/day (2013)
+
* Production Volume: 85 000 barrels/day (2013)
Description
 
  
The water depth in the area is 300 - 350 metres.
+
=== Description ===
Snorre A in the south is a floating steel facility (TLP) for accommodation, drilling and processing. Snorre A also has a separate process module for production from the Vigdis field. A subsea template with ten well slots, Snorre UPA, is located centrally on the field and connected to Snorre A.
 
Snorre B is located in the northern part of the field, and is a semi-submersible integrated drilling, processing and accommodation facility. An amended PDO for Snorre, including a new processing module on Snorre A for processing oil from Vigdis, was approved in December 1994. The PDO for Snorre B was approved in June 1998. Snorre B came on stream in June 2001.
 
Snorre C is a TLP which will be added to the field
 
Oil and gas are separated in two stages at Snorre A before transport in separate pipelines to Statfjord A for final processing and export. The oil is loaded onto shuttle tankers at Statfjord and excess gas is sent through the Statpipe Gas Pipeline to Kårstø, or through Tampen Link to St Fergus. Processed oil from Snorre B is routed by pipeline to Statfjord B for storage and loading to shuttle tankers.
 
All gas from Snorre B is normally re-injected, but may also be sent to Snorre A for injection or export.
 
Contractors
 
  
Dragados: Snorre B Semi-sub
+
* The water depth in the area is 300 - 350 metres.
Kvaerner Rosenberg: Snorre TLP
+
* Snorre A in the south is a floating steel facility (TLP) for accommodation, drilling and processing. Snorre A also has a separate process module for production from the [[Vigdis Oil and Gas Field]]. A subsea template with ten well slots, Snorre UPA, is located centrally on the field and connected to Snorre A.
Kvaerner:
+
* Snorre B is located in the northern part of the field, and is a semi-submersible integrated drilling, processing and accommodation facility. An amended PDO for Snorre, including a new processing module on Snorre A for processing oil from Vigdis, was approved in December 1994. The PDO for Snorre B was approved in June 1998. Snorre B came on stream in June 2001.
TLP Well Template and Piles
+
* Snorre C is a TLP which will be added to the field
Drilling Derrick, Sub-structure and Skidbase
+
* Oil and gas are separated in two stages at Snorre A before transport in separate pipelines to Statfjord A for final processing and export. The oil is loaded onto shuttle tankers at Statfjord and excess gas is sent through the [[Statpipe Gas Pipeline]] to Kårstø, or through Tampen Link to St Fergus. Processed oil from Snorre B is routed by pipeline to Statfjord B for storage and loading to shuttle tankers.
Snorre B - Deck Sections
+
* All gas from Snorre B is normally re-injected, but may also be sent to Snorre A for injection or export.
ABB: Snorre B - Engineering, procurement, as well as contracting and full installation, delivery of four templates with manifolds, wellhead, trees and control systems for 27 subsea wells as well as control umbilicals
+
* The field is produced with pressure support from water injection, gas injection and water alternating gas injection (WAG).
Emtunga: A60 fire pump modules
+
* The Snorre Expansion Project (SEP) consists of six subsea templates, each with four wells
Aibel: Engineering, procurement, fabrication and installation of major modification work on the Snorre platforms related to Snorre Export and Robustness
+
 
Aker Solutions: Deliver replacement and upgrading of the drilling equipment and systems on the Snorre A platform
+
=== Contractors ===
FMC Technologies:
+
 
10 production risers and tieback connectors
+
* Dragados: Snorre B Semi-sub
Replacement workover system
+
* Kvaerner Rosenberg: Snorre TLP
Snorre C
+
* Kvaerner:
 +
** TLP Well Template and Piles
 +
** Drilling Derrick, Sub-structure and Skidbase
 +
** Snorre B - Deck Sections
 +
* Leirvik
 +
** Snorre A VKM & Installation New Office and Workshop module including Hook-Up
 +
** Snorre A LQE & Installation 46 new cabins, CCR etc. in one module including Hook-Up
 +
* ABB: Snorre B - Engineering, procurement, as well as contracting and full installation, delivery of four templates with manifolds, wellhead, trees and control systems for 27 subsea wells as well as control umbilicals
 +
* Emtunga: A60 fire pump modules
 +
* Aibel: Engineering, procurement, fabrication and installation of major modification work on the Snorre platforms related to Snorre Export and Robustness
 +
* Aker Solutions: Deliver replacement and upgrading of the drilling equipment and systems on the Snorre A platform
 +
* FMC Technologies:
 +
** 10 production risers and tieback connectors
 +
** Replacement workover system
 +
==== Snorre C ====
 +
 
 +
* Wood Group Mustang: Engineering services for Snorre C platform
  
Wood Group Mustang: Engineering services for Snorre C platform
 
 
=== History ===
 
=== History ===
  
1979 - Snorre Oil Field discovered
+
* 1979 - Snorre Oil Field discovered
1992 - First oil produced
+
* 1992 - First oil produced
1998 - The PDO for Snorre B was approved
+
* 1998 - The PDO for Snorre B was approved
2001 - Snorre B came on stream
+
* 2001 - Snorre B came on stream
2010 - Aibel awarded contract for platform modifications
+
* 2010 - Aibel awarded contract for platform modifications
2012 - Aker Solutions awarded contract for replacement and upgrading of the drilling equipment and systems on the Snorre A platform
+
* 2012 - Aker Solutions awarded contract for replacement and upgrading of the drilling equipment and systems on the Snorre A platform
2012 - Statoil announced it was to install seismic cables on the seabed to increase oil recovery
+
* 2012 - Statoil announced it was to install seismic cables on the seabed to increase oil recovery
2013 - Statoil recommends a third platform to increase recovery
+
* 2013 - Statoil recommends a third platform to increase recovery
2014 - Temporary shut down on Snorre B due to erosion beneath the template
+
* 2014 - Temporary shut down on Snorre B due to erosion beneath the template
 +
* 2018 - Approval for expansion project
 +
* 2020 - Snorre expansion project starts production
 +
* 2022 - Hywind Tampen wind farm begins supplying power to the platforms
 +
 
 
=== Geology ===
 
=== Geology ===
  
The Snorre field consists of several large fault blocks. The reservoir contains Lower Jurassic and Triassic sandstones in the Statfjord and Lunde Formations. The reservoir depth is 2 000 - 2 700 metres. The reservoir has a complex structure with many alluvial channels and internal flow barriers.
+
* The Snorre field consists of several large fault blocks. The reservoir contains Lower Jurassic and Triassic sandstones in the Statfjord and Lunde Formations.  
 
+
* The reservoir depth is 2 000 - 2 700 metres. The reservoir has a complex structure with many alluvial channels and internal flow barriers.
  
 
=== Links ===
 
=== Links ===
Line 60: Line 72:
 
# [[Kvaerner Platform References]]
 
# [[Kvaerner Platform References]]
 
# [[Kvaerner Topsides References]]
 
# [[Kvaerner Topsides References]]
 +
# [[Leirvik Living quarters and extensions References]]
 
# [http://killajoules.wikidot.com/archive:snorre-export-topside-and-robustness-contract-to-aib Snorre Export Topside and Robustness contract to Aibel AS]
 
# [http://killajoules.wikidot.com/archive:snorre-export-topside-and-robustness-contract-to-aib Snorre Export Topside and Robustness contract to Aibel AS]
 
# [http://killajoules.wikidot.com/archive:abb-wins-us-160-million-contract-for-subsea-oil-inst ABB wins US$ 160-million contract for subsea oil installations]
 
# [http://killajoules.wikidot.com/archive:abb-wins-us-160-million-contract-for-subsea-oil-inst ABB wins US$ 160-million contract for subsea oil installations]
Line 69: Line 82:
 
# [http://killajoules.wikidot.com/blog:5186 Production from Snorre B template shut down]
 
# [http://killajoules.wikidot.com/blog:5186 Production from Snorre B template shut down]
 
# [http://killajoules.wikidot.com/blog:5496 Wood Group Mustang selected to provide engineering services for Statoil Snorre C platform]
 
# [http://killajoules.wikidot.com/blog:5496 Wood Group Mustang selected to provide engineering services for Statoil Snorre C platform]
 +
# [https://abarrelfull.blogspot.com/2023/01/snorre-expansion-project-begins.html Snorre Expansion Project begins production]
 +
# [https://a-barrel-full.blogspot.com/2022/11/first-power-from-hywind-tampen.html First power from Hywind Tampen]
 +
 +
[[category:Field]]
 +
[[category:Norway]]
 +
[[category:Equinor]]

Latest revision as of 11:36, 6 January 2023

Summary Information

  • Operator: Equinor
  • Country: Norway
  • Location: Tampen area in the northern part of the North Sea
  • Production start: 1992
  • Partners: Statoil - 33.28%, Petoro - 30.0%, ExxonMobil - 17.45%, Idemitsu - 9.6%, RWE Dea - 8.57% and Core Energy 1.11%
  • Type: Oil
  • Estimated Reserves: Original
    • 249.9 million Sm³ oil
    • 6.6 billion Sm³ gas
    • 4.7 million tonnes NGL
  • Production Volume: 85 000 barrels/day (2013)

Description

  • The water depth in the area is 300 - 350 metres.
  • Snorre A in the south is a floating steel facility (TLP) for accommodation, drilling and processing. Snorre A also has a separate process module for production from the Vigdis Oil and Gas Field. A subsea template with ten well slots, Snorre UPA, is located centrally on the field and connected to Snorre A.
  • Snorre B is located in the northern part of the field, and is a semi-submersible integrated drilling, processing and accommodation facility. An amended PDO for Snorre, including a new processing module on Snorre A for processing oil from Vigdis, was approved in December 1994. The PDO for Snorre B was approved in June 1998. Snorre B came on stream in June 2001.
  • Snorre C is a TLP which will be added to the field
  • Oil and gas are separated in two stages at Snorre A before transport in separate pipelines to Statfjord A for final processing and export. The oil is loaded onto shuttle tankers at Statfjord and excess gas is sent through the Statpipe Gas Pipeline to Kårstø, or through Tampen Link to St Fergus. Processed oil from Snorre B is routed by pipeline to Statfjord B for storage and loading to shuttle tankers.
  • All gas from Snorre B is normally re-injected, but may also be sent to Snorre A for injection or export.
  • The field is produced with pressure support from water injection, gas injection and water alternating gas injection (WAG).
  • The Snorre Expansion Project (SEP) consists of six subsea templates, each with four wells

Contractors

  • Dragados: Snorre B Semi-sub
  • Kvaerner Rosenberg: Snorre TLP
  • Kvaerner:
    • TLP Well Template and Piles
    • Drilling Derrick, Sub-structure and Skidbase
    • Snorre B - Deck Sections
  • Leirvik
    • Snorre A VKM & Installation New Office and Workshop module including Hook-Up
    • Snorre A LQE & Installation 46 new cabins, CCR etc. in one module including Hook-Up
  • ABB: Snorre B - Engineering, procurement, as well as contracting and full installation, delivery of four templates with manifolds, wellhead, trees and control systems for 27 subsea wells as well as control umbilicals
  • Emtunga: A60 fire pump modules
  • Aibel: Engineering, procurement, fabrication and installation of major modification work on the Snorre platforms related to Snorre Export and Robustness
  • Aker Solutions: Deliver replacement and upgrading of the drilling equipment and systems on the Snorre A platform
  • FMC Technologies:
    • 10 production risers and tieback connectors
    • Replacement workover system

Snorre C

  • Wood Group Mustang: Engineering services for Snorre C platform

History

  • 1979 - Snorre Oil Field discovered
  • 1992 - First oil produced
  • 1998 - The PDO for Snorre B was approved
  • 2001 - Snorre B came on stream
  • 2010 - Aibel awarded contract for platform modifications
  • 2012 - Aker Solutions awarded contract for replacement and upgrading of the drilling equipment and systems on the Snorre A platform
  • 2012 - Statoil announced it was to install seismic cables on the seabed to increase oil recovery
  • 2013 - Statoil recommends a third platform to increase recovery
  • 2014 - Temporary shut down on Snorre B due to erosion beneath the template
  • 2018 - Approval for expansion project
  • 2020 - Snorre expansion project starts production
  • 2022 - Hywind Tampen wind farm begins supplying power to the platforms

Geology

  • The Snorre field consists of several large fault blocks. The reservoir contains Lower Jurassic and Triassic sandstones in the Statfjord and Lunde Formations.
  • The reservoir depth is 2 000 - 2 700 metres. The reservoir has a complex structure with many alluvial channels and internal flow barriers.

Links

  1. NPD, Snorre
  2. Jotun FPSO References
  3. Emtunga Europe Offshore Platform References
  4. Kvaerner Platform References
  5. Kvaerner Topsides References
  6. Leirvik Living quarters and extensions References
  7. Snorre Export Topside and Robustness contract to Aibel AS
  8. ABB wins US$ 160-million contract for subsea oil installations
  9. Aker Solutions wins Snorre A Drilling Facilities contract
  10. Seismic cables on the seabed to increase oil recovery
  11. FMC Technologies Receives $33 Million Subsea Equipment Order for Statoil's Snorre Field
  12. Platform solution recommended to maximise Snorre production
  13. FMC Technologies to Supply Statoil With $114 Million Workover System for Snorre B Platform
  14. Production from Snorre B template shut down
  15. Wood Group Mustang selected to provide engineering services for Statoil Snorre C platform
  16. Snorre Expansion Project begins production
  17. First power from Hywind Tampen