Difference between revisions of "Anning and Somerville Gas Fields"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Operator: * Country: UK * Location: Southern North Sea * Production start: * Partners: * Type: Oil / Gas * Estimated Reserves: * Production V...") |
Abarrelfull (talk | contribs) |
||
| (5 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
=== Summary Information === | === Summary Information === | ||
| − | * Operator: | + | * Operator: Hartshead |
* Country: UK | * Country: UK | ||
* Location: Southern North Sea | * Location: Southern North Sea | ||
* Production start: | * Production start: | ||
* Partners: | * Partners: | ||
| − | * Type: | + | * Type: Gas |
| − | * Estimated Reserves: | + | * Estimated Reserves: 2P Gas Reserves of 301.5 Bcf (52 MMboe). |
| − | * Production Volume: | + | * Production Volume: |
=== Description === | === Description === | ||
* The development concept consists of six production wells from two wireline capable Normally Unmanned Installation (NUI) platforms at Anning and Somerville. | * The development concept consists of six production wells from two wireline capable Normally Unmanned Installation (NUI) platforms at Anning and Somerville. | ||
| − | * These platforms will then connect via a subsea pipeline to third party infrastructure for onward transportation and processing to entry into the UK gas network | + | * These platforms will then connect via a subsea pipeline to third party infrastructure for onward transportation and processing to entry into the UK gas network. A pipeline to the [[Leman Gas Fields]] is being considered |
* Final Investment Decision (FID) is expected in 2023 and first gas in late 2024 | * Final Investment Decision (FID) is expected in 2023 and first gas in late 2024 | ||
=== Contractors === | === Contractors === | ||
| − | * - | + | * Petrofac: offshore construction support for the subsea pipeline tie-in activities on the Corvette to Leman Alpha export pipeline, communication connections, pipework for system control and export route options and control room integration. |
=== History === | === History === | ||
| − | * 2022 - | + | * 2022 - Submission made to the North Sea Transition Authority |
| + | * 2022 - Petrofac selected for engineering study | ||
=== Geology === | === Geology === | ||
| Line 24: | Line 25: | ||
=== Links === | === Links === | ||
| − | # [https://hartshead-resources.com.au/united-kingdom/ ] | + | # [https://hartshead-resources.com.au/united-kingdom/ Hartshead, Projects] |
| + | # [https://a-barrel-full.blogspot.com/2022/11/maximising-economic-recovery-in-uks.html Maximising economic recovery in the UK’s Southern North Sea for Shell and Hartshead Resources Sea for Shell and Hartshead Resources] | ||
[[category:Field]] | [[category:Field]] | ||
[[category:UK]] | [[category:UK]] | ||
| − | [[category: | + | [[category:Hartshead]] |
Latest revision as of 10:38, 5 November 2022
Summary Information
- Operator: Hartshead
- Country: UK
- Location: Southern North Sea
- Production start:
- Partners:
- Type: Gas
- Estimated Reserves: 2P Gas Reserves of 301.5 Bcf (52 MMboe).
- Production Volume:
Description
- The development concept consists of six production wells from two wireline capable Normally Unmanned Installation (NUI) platforms at Anning and Somerville.
- These platforms will then connect via a subsea pipeline to third party infrastructure for onward transportation and processing to entry into the UK gas network. A pipeline to the Leman Gas Fields is being considered
- Final Investment Decision (FID) is expected in 2023 and first gas in late 2024
Contractors
- Petrofac: offshore construction support for the subsea pipeline tie-in activities on the Corvette to Leman Alpha export pipeline, communication connections, pipework for system control and export route options and control room integration.
History
- 2022 - Submission made to the North Sea Transition Authority
- 2022 - Petrofac selected for engineering study