Abarrelfull (talk | contribs) (Created page with "Summary Information * Operator: ENI * Country: Angola * Location: Block 15/06, Offshore * Production start: * Partners: ENI - 35%, Sonangol - 55%, Falcon Oil - 5%, Petrobra...") |
Abarrelfull (talk | contribs) |
||
Line 1: | Line 1: | ||
− | Summary Information | + | === Summary Information === |
* Operator: ENI | * Operator: ENI | ||
* Country: Angola | * Country: Angola | ||
Line 9: | Line 9: | ||
* Production Volume: | * Production Volume: | ||
− | + | === Description === | |
* The East Hub project foresees the production of the Cabaça North and South-East discoveries | * The East Hub project foresees the production of the Cabaça North and South-East discoveries | ||
− | * It will utilise the | + | * It will utilise the [[Armada Cabaca FPSO]], converted from a VLCC class tanker |
* The FPSO will utilise an external turret with 18 risers and umbilicals connected to the turret. The FPSO will also have a storage capacity of 1,800,000 barrels while having a crude oil production rate of 80,000 bopd* oil production, 120,000 bwpd* water injection and 120,000 MMscf* gas handling capacities. | * The FPSO will utilise an external turret with 18 risers and umbilicals connected to the turret. The FPSO will also have a storage capacity of 1,800,000 barrels while having a crude oil production rate of 80,000 bopd* oil production, 120,000 bwpd* water injection and 120,000 MMscf* gas handling capacities. | ||
− | + | === Contractors === | |
* **Bumi Armada:** Supply and operation of FPSO | * **Bumi Armada:** Supply and operation of FPSO | ||
* **Keppel:** FPSO conversion including refurbishment and life extension works, upgrading of living quarters to accommodate 100 personnel, installation and integration of an external turret mooring system and topside process modules | * **Keppel:** FPSO conversion including refurbishment and life extension works, upgrading of living quarters to accommodate 100 personnel, installation and integration of an external turret mooring system and topside process modules | ||
* **FMC Technologies:** | * **FMC Technologies:** | ||
− | + | ** Subsea production systems | |
− | + | ** subsea multiphase boosting pumps, manifolds, and installation support services | |
* **Technip:** Project management and manufacture of about 15 kilometers of dynamic and static steel tube umbilicals | * **Technip:** Project management and manufacture of about 15 kilometers of dynamic and static steel tube umbilicals | ||
− | + | === History === | |
* 2006 - ENI awarded the block | * 2006 - ENI awarded the block | ||
* 2009 - Cabaça North discovered | * 2009 - Cabaça North discovered | ||
Line 29: | Line 29: | ||
− | + | === Geology === | |
* | * | ||
Revision as of 06:28, 9 August 2022
Summary Information
- Operator: ENI
- Country: Angola
- Location: Block 15/06, Offshore
- Production start:
- Partners: ENI - 35%, Sonangol - 55%, Falcon Oil - 5%, Petrobras - 5%
- Type: Oil & Gas
- Estimated Reserves:
- Production Volume:
Description
- The East Hub project foresees the production of the Cabaça North and South-East discoveries
- It will utilise the Armada Cabaca FPSO, converted from a VLCC class tanker
- The FPSO will utilise an external turret with 18 risers and umbilicals connected to the turret. The FPSO will also have a storage capacity of 1,800,000 barrels while having a crude oil production rate of 80,000 bopd* oil production, 120,000 bwpd* water injection and 120,000 MMscf* gas handling capacities.
Contractors
- **Bumi Armada:** Supply and operation of FPSO
- **Keppel:** FPSO conversion including refurbishment and life extension works, upgrading of living quarters to accommodate 100 personnel, installation and integration of an external turret mooring system and topside process modules
- **FMC Technologies:**
- Subsea production systems
- subsea multiphase boosting pumps, manifolds, and installation support services
- **Technip:** Project management and manufacture of about 15 kilometers of dynamic and static steel tube umbilicals
History
- 2006 - ENI awarded the block
- 2009 - Cabaça North discovered
- 2010 - Cabaca South East discovered
- 2014 - Bumi Armada awarded FPSO contract
Geology
Links
- ENI in Angola
- Eni signs Production Sharing Contract for exploration Block 15/06 in Angolan deepwater
- Eni makes a new significant oil discovery offshore Angola
- Eni: major oil discovery offshore Angola
- Bumi Armada Signs FPSO Contract With ENI For The Chartering, Operations And Maintenance For Block 15/06, Angola
- Keppel secures S$153 million in contracts from repeat customers
- FMC Technologies Awarded $393 Million Subsea Systems Contract for Eni's Block 15/06 East Hub Project Offshore Angola
- Technip awarded umbilical supply contract by ENI
- FMC Technologies Awarded Subsea Contract for Eni's Block 15/06 West Hub Development