| * Project Type: Upgrade | * Project Type: Upgrade | ||
| − | * Project Summary: | + | * Project Summary: A bottom of the barrel project utilising a delayed coker | 
| * Main Contractors | * Main Contractors | ||
| − | ** | + | ** Lummus: 2 fired heaters | 
| * Licences | * Licences | ||
| − | **   | + | ** Chevron Lummus Global: Delayed Coker Unit | 
| === Refining Units === | === Refining Units === | ||
Revision as of 14:49, 11 January 2022
Contents
Summary Information
- Ownership:
- Website:
- Wiki Page:
- Location:
- Capacity: million tons/annum & 00,000 bbl/day
- Nelson Complexity:
- Project Stage:
- Expected Completion: 201X
- Budget:
The Project
- Project Type: Upgrade
- Project Summary: A bottom of the barrel project utilising a delayed coker
- Main Contractors
- Lummus: 2 fired heaters
 
- Licences
- Chevron Lummus Global: Delayed Coker Unit
 
Refining Units
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
-
Products Produced
-
History
- 2018 - Chevron Lummus Global awarded licence for DCU