Difference between revisions of "Hassi Messaoud Refinery Project"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
| (2 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
=== Summary Information === | === Summary Information === | ||
| − | Ownership: Sonatrach | + | * Ownership: Sonatrach |
| − | Website: | + | * Website: |
| − | Wiki Page: | + | * Wiki Page: |
| − | Location: Hassi Messaoud, Algeria | + | * Location: Hassi Messaoud, Algeria |
| − | Capacity: 5.0 million tons/annum & 100,000 bbl/day | + | * Capacity: 5.0 million tons/annum & 100,000 bbl/day |
| − | Nelson Complexity: | + | * Nelson Complexity: |
| − | Project Stage: | + | * Project Stage: Under construction |
| − | Expected Completion: | + | * Expected Completion: 2024 |
| − | Budget: | + | * Budget: $3.7 billion |
| + | |||
=== The Project === | === The Project === | ||
| − | Project Type: Greenfield Refinery | + | * Project Type: Greenfield Refinery |
| − | Project Summary: a new deep-conversion crude oil Refinery with a capacity of 5 Million Tonnes per year | + | * Project Summary: a new deep-conversion crude oil Refinery with a capacity of 5 Million Tonnes per year |
| − | Main Contractors | + | * Main Contractors |
| − | Refining Units | + | ** Samsung Engineering & Técnicas Reunidas were awarded the EPC contract |
| + | === Refining Units === | ||
| + | * Crude Distillation Unit (CDU) | ||
| + | * Vacuum Distillation Unit (VDU), | ||
| + | * Continuous Catalytic reforming (CCR) Unit, | ||
| + | * Isomerization, | ||
| + | * Naphtha Hydro-treating(NHT) Unit, | ||
| + | * Hydrodesulfurization(HDS) Unit, | ||
| + | * Hydrocracker Unit (HCU) | ||
| + | === Terminal Capacity === | ||
| + | * Crude Oil: | ||
| + | * Refined Products: | ||
| + | === Crude Supply === | ||
| + | * The refinery will be supplied with local produced crude oil | ||
| + | |||
| + | === Products Produced === | ||
- | - | ||
| − | + | === History === | |
| − | + | * 2018 - Tender for construction | |
| − | + | * 2020 - Samsung and Técnicas awarded EPC contract | |
| − | + | === Other Information === | |
- | - | ||
| − | + | === Links === | |
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
Opening of the folds For the Hassi Messaoud Refinery project | Opening of the folds For the Hassi Messaoud Refinery project | ||
| + | # [https://a-barrel-full.blogspot.com/2020/09/samsung-engineering-wins-sonatrach.html Samsung Engineering wins the Sonatrach Hassi Messaoud Refinery in Algeria] | ||
Latest revision as of 08:01, 29 September 2020
Contents
Summary Information
- Ownership: Sonatrach
- Website:
- Wiki Page:
- Location: Hassi Messaoud, Algeria
- Capacity: 5.0 million tons/annum & 100,000 bbl/day
- Nelson Complexity:
- Project Stage: Under construction
- Expected Completion: 2024
- Budget: $3.7 billion
The Project
- Project Type: Greenfield Refinery
- Project Summary: a new deep-conversion crude oil Refinery with a capacity of 5 Million Tonnes per year
- Main Contractors
- Samsung Engineering & Técnicas Reunidas were awarded the EPC contract
Refining Units
- Crude Distillation Unit (CDU)
- Vacuum Distillation Unit (VDU),
- Continuous Catalytic reforming (CCR) Unit,
- Isomerization,
- Naphtha Hydro-treating(NHT) Unit,
- Hydrodesulfurization(HDS) Unit,
- Hydrocracker Unit (HCU)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- The refinery will be supplied with local produced crude oil
Products Produced
-
History
- 2018 - Tender for construction
- 2020 - Samsung and Técnicas awarded EPC contract
Other Information
-
Links