=== The Project ===
Project Type: Upgrade
+
* Project Type: Upgrade
Project Summary:
+
* Project Summary:
Construction of delayed coking unit with annual capacity of 1 mln tons (to be commissioned during 2011)
+
** Construction of delayed coking unit with annual capacity of 1 mln tons (to be commissioned during 2011)
Construction of a unit for hydrotreatment of diesel fuel by 2011
+
** Construction of a unit for hydrotreatment of diesel fuel by 2011
Construction of a hydrocracker complex
+
** Construction of a hydrocracker complex
Construction of a FCC unit by 2015
+
** Construction of a FCC unit by 2015
=== Main Contractors
+
=== Main Contractors ===
Técnicas Reunidas:
+
* Técnicas Reunidas:
Front End Engineering and Design (FEED) of a hydrocracker complex
+
** Front End Engineering and Design (FEED) of a hydrocracker complex
Engineering and supply of the equipment and materials, construction, pre-commissioning as well as support for commissioning of hydrocracker complex
+
** Engineering and supply of the equipment and materials, construction, pre-commissioning as well as support for commissioning of hydrocracker complex
VNIPIneft won the tender and signed a contract to design the distillation column
+
* VNIPIneft won the tender and signed a contract to design the distillation column
=== Refining Units
+
=== Refining Units ===
hydrocracker complex - 3.5 Million tpa
+
* hydrocracker complex - 3.5 Million tpa
Delayed Coker - Will replace 2 existing obsolete units
+
* Delayed Coker - Will replace 2 existing obsolete units
Fluidised Catalytic Cracker - 1.5 Million tpa
+
* Fluidised Catalytic Cracker - 1.5 Million tpa
Diesel Hydrotreatment
+
* Diesel Hydrotreatment
=== Terminal Capacity
+
=== Terminal Capacity ===
Crude Oil:
+
* Crude Oil:
Refined Products:
+
* Refined Products:
=== Crude Supply
+
=== Crude Supply ===
Refines a blend of light West Siberian and Lower Volga crudes
+
* Refines a blend of light West Siberian and Lower Volga crudes
Products Produced
+
=== Products Produced ===
The project will increase the proportion of light products
+
* The project increased the proportion of light products
The project will increase the output of Euro-5 diesel fuel by 2,4 million tonnes per year
+
* The project increased the output of Euro-5 diesel fuel by 2,4 million tonnes per year
 +
 
 
=== History ===
 
=== History ===
 
2011 - Tecnicas Reunidas awarded the FEED for the hydrocracker complex
 
2011 - Tecnicas Reunidas awarded the FEED for the hydrocracker complex

Revision as of 18:54, 19 March 2020

Summary Information

  • Ownership: Lukoil
  • Website: http://www.lukoil.com/
  • List of Lukoil Refineries
  • Wiki Page: Volgograd Refinery
  • Location: Volvograd, Southern Russia
  • Capacity:
    • Before: 11.25 million tons/annum & 225.000 bbl/day
    • After: 14.5 million tons/annum & 290.000 bbl/day
  • Nelson Complexity: 6.9
  • Project Stage: Completed 2016
  • Budget:

The Project

  • Project Type: Upgrade
  • Project Summary:
    • Construction of delayed coking unit with annual capacity of 1 mln tons (to be commissioned during 2011)
    • Construction of a unit for hydrotreatment of diesel fuel by 2011
    • Construction of a hydrocracker complex
    • Construction of a FCC unit by 2015

Main Contractors

  • Técnicas Reunidas:
    • Front End Engineering and Design (FEED) of a hydrocracker complex
    • Engineering and supply of the equipment and materials, construction, pre-commissioning as well as support for commissioning of hydrocracker complex
  • VNIPIneft won the tender and signed a contract to design the distillation column

Refining Units

  • hydrocracker complex - 3.5 Million tpa
  • Delayed Coker - Will replace 2 existing obsolete units
  • Fluidised Catalytic Cracker - 1.5 Million tpa
  • Diesel Hydrotreatment

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • Refines a blend of light West Siberian and Lower Volga crudes

Products Produced

  • The project increased the proportion of light products
  • The project increased the output of Euro-5 diesel fuel by 2,4 million tonnes per year

History

2011 - Tecnicas Reunidas awarded the FEED for the hydrocracker complex 2011 - Construction of the delayed coker completed 2013 - Técnicas Reunidas awarded EPC contract for the hydrocracker complex

Other Information

-

Links

  1. Oil Refining in Russia. Majors Plan Upgrades to Raise Product Quality
  2. Técnicas Reunidas awarded a Project in Russia and another in Turkey
  3. LUKoil finished building a delayed coking unit at the Volgograd Refinery
  4. Design Installation ELOU-AVT-6 OAO LUKOIL-Volgogradneftepererabotka
  5. LUKOIL refineries development strategy
  6. Lukoil Launches A Major Modernization Project At Volgograd Refinery
  7. Técnicas Reunidas has been awarded a major contract for the Lukoil´s refinery in Volgodgrad, Russia