Difference between revisions of "Volgograd Refinery Project"

From A Barrel Full
Jump to navigation Jump to search
 
(One intermediate revision by the same user not shown)
Line 42: Line 42:
 
* 2011 - Construction of the delayed coker completed
 
* 2011 - Construction of the delayed coker completed
 
* 2013 - Técnicas Reunidas awarded EPC contract for the hydrocracker complex
 
* 2013 - Técnicas Reunidas awarded EPC contract for the hydrocracker complex
8 2016 - The project was completed
+
* 2016 - The project was completed
  
 
=== Other Information ===
 
=== Other Information ===
Line 48: Line 48:
 
=== Links ===
 
=== Links ===
 
# [http://www.oilandgaseurasia.com/articles/p/70/article/586/ Oil Refining in Russia. Majors Plan Upgrades to Raise Product Quality]
 
# [http://www.oilandgaseurasia.com/articles/p/70/article/586/ Oil Refining in Russia. Majors Plan Upgrades to Raise Product Quality]
 +
# [[VNIPIneft Refinery Project References]]
 
# [http://killajoules.wikidot.com/archive:tecnicas-reunidas-awarded-a-project-in-russia-and-an Técnicas Reunidas awarded a Project in Russia and another in Turkey]
 
# [http://killajoules.wikidot.com/archive:tecnicas-reunidas-awarded-a-project-in-russia-and-an Técnicas Reunidas awarded a Project in Russia and another in Turkey]
 
# [http://killajoules.wikidot.com/blog:1617 LUKoil finished building a delayed coking unit at the Volgograd Refinery]  
 
# [http://killajoules.wikidot.com/blog:1617 LUKoil finished building a delayed coking unit at the Volgograd Refinery]  

Latest revision as of 22:28, 21 March 2020

Summary Information

  • Ownership: Lukoil
  • Website: http://www.lukoil.com/
  • List of Lukoil Refineries
  • Wiki Page: Volgograd Refinery
  • Location: Volvograd, Southern Russia
  • Capacity:
    • Before: 11.25 million tons/annum & 225.000 bbl/day
    • After: 14.5 million tons/annum & 290.000 bbl/day
  • Nelson Complexity: 6.9
  • Project Stage: Completed 2016
  • Budget:

The Project

  • Project Type: Upgrade
  • Project Summary:
    • Construction of delayed coking unit with annual capacity of 1 mln tons (to be commissioned during 2011)
    • Construction of a unit for hydrotreatment of diesel fuel by 2011
    • Construction of a hydrocracker complex
    • Construction of a FCC unit by 2015

Main Contractors

  • Técnicas Reunidas:
    • Front End Engineering and Design (FEED) of a hydrocracker complex
    • Engineering and supply of the equipment and materials, construction, pre-commissioning as well as support for commissioning of hydrocracker complex
  • VNIPIneft won the tender and signed a contract to design the distillation column

Refining Units

  • hydrocracker complex - 3.5 Million tpa
  • Delayed Coker - Will replace 2 existing obsolete units
  • Fluidised Catalytic Cracker - 1.5 Million tpa
  • Diesel Hydrotreatment

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • Refines a blend of light West Siberian and Lower Volga crudes

Products Produced

  • The project increased the proportion of light products
  • The project increased the output of Euro-5 diesel fuel by 2,4 million tonnes per year

History

  • 2011 - Tecnicas Reunidas awarded the FEED for the hydrocracker complex
  • 2011 - Construction of the delayed coker completed
  • 2013 - Técnicas Reunidas awarded EPC contract for the hydrocracker complex
  • 2016 - The project was completed

Other Information

-

Links

  1. Oil Refining in Russia. Majors Plan Upgrades to Raise Product Quality
  2. VNIPIneft Refinery Project References
  3. Técnicas Reunidas awarded a Project in Russia and another in Turkey
  4. LUKoil finished building a delayed coking unit at the Volgograd Refinery
  5. Design Installation ELOU-AVT-6 OAO LUKOIL-Volgogradneftepererabotka
  6. LUKOIL refineries development strategy
  7. Lukoil Launches A Major Modernization Project At Volgograd Refinery
  8. Técnicas Reunidas has been awarded a major contract for the Lukoil´s refinery in Volgodgrad, Russia
  9. Lukoil Commissions VGO Deep Conversion Complex