VNIPIneft Refinery Project References

From A Barrel Full
Revision as of 19:34, 21 March 2020 by Abarrelfull (talk | contribs) (Created page with "OAO TatneftHydrocrackingComplex, 2.9 MTA – 2014 OAO VNIPIneft Scope of Work: Authority Engineering,DetailedDesign, Procurement, Supervision. ZAO RNPK VGO Hydrocracking Compl...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

OAO TatneftHydrocrackingComplex, 2.9 MTA – 2014 OAO VNIPIneft Scope of Work: Authority Engineering,DetailedDesign, Procurement, Supervision. ZAO RNPK VGO Hydrocracking Complex,2 MTA – 2014 OAO VNIPIneft Scope of Work: Authority Engineering Sulfur Recovery Unit at the MMC Norilsk Nickel Polar Division Copper Plant - 2014 OAOVNIPIneftScopeofWork: AuthorityEngineering OOO LUKOIL-Volgogradneftepererabotka Integrated CDU/VDU, 6 MTA - 2014 OAOVNIPIneftScopeofWork: Authority Engineering and Detailed Design OAO Gazprom Neft – Moscow Refinery Isomerization Unit, 650 kTA – 2013 OAOVNIPIneftScopeofWork: Basic Design Acceptance, Detailed Design,Supervision OAO Gazprom Neft – Moscow Refinery Diesel Hydrotreating Unit, 320 kTA- 2013 OAOVNIPIneftScopeofWork: Authority Engineering and Detailed Design, Supervision OOO LUKOIL-Volgogradneftepererabotka Atmospheric – Vacuum Distillation Unit - 2012 OAOVNIPIneftScopeofWork: Authority Engineering OAO Angarskneftekhimproyekt Diesel Hydrotreating Unit- 2012 OAOVNIPIneftScopeofWork: Authority Engineering OAO Gazprom Neft – Moscow RefineryPSA Unit - 2011 OAOVNIPIneftScopeofWork:Authority Engineering and Detailed Design, Supervision OJSC TANECO CDU/VDU, 7 MTA - 2010 OAOVNIPIneftScopeofWork: Basic Design, Authority Engineering and Detailed Design, Procurement, Supervision OOO PO Kirishinefteorgsintez Capacity: 4.9 MTA (vacuum distillation), 2.2 MTA (visbreaking) OAOVNIPIneftScopeofWork: Basic Design Acceptance; Detailed Design, Procurement. Commissioningdate: 2009 ZAO RNPK Deep Conversion Complex Capacity: 2.5 MTA OAOVNIPIneftScopeofWork: BasicDesignAcceptance, AuthorityEngineeringandDetailedDesign(jointlywithCB&ILummus); Procurement; Supervision. Commissioningdate: 2005-2006 OAO TAIF-NK Catalytic Cracking Complex Capacity: 850 kTA OAOVNIPIneftScopeofWork: ActingasaGeneralDesigner; BasicDesign(jointly with OAO VNIINP);DetailedDesign; Procurement; Supervision. Commissioningdate: 2005

  • Yanos Yaroslavl Refinery
    • OAO Slavneft-Yaroslavnefteorgsintez Deep Conversion Complex
    • Capacity: 2.1 MTA
    • Scope of Work: Basic Design Acceptance, Detailed Design(jointly with Toyo Engineering Corporation); Supervision.
    • Commissioning date: 2005

OOO LUKOIL-Permnefteorgsintez VGO Hydrocracking Complex Capacity: 3.5 MTA - Plant OAOVNIPIneftScopeofWork: ActingasaGeneralDesigner; Basic Design Acceptance; DetailedDesign, Procurement, Supervision. Commissioning date: 2004 ZAO RNPK Catalytic Cracking Complex Capacity: 2.5 MTA OAOVNIPIneftScopeofWork: DetailedDesign, Supervision. Commissioning date: 2001

  1. [1]