Difference between revisions of "Snam Adriatic Floating LNG Terminal"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 15: | Line 15: | ||
* Unloading capacity: | * Unloading capacity: | ||
* Send out capacity: 5BCM/annum | * Send out capacity: 5BCM/annum | ||
− | * Constructor: | + | * Constructor: |
+ | ** Corinth Pipeworks: manufacture and supply approximately 13 km of longitudinally submerged arc-welded steel pipes | ||
=== Ongoing Projects/Project Status === | === Ongoing Projects/Project Status === | ||
Line 35: | Line 36: | ||
=== Links === | === Links === | ||
# [https://lng-news.blogspot.com/2022/07/snam-purchases-new-floating.html Snam Purchases New Floating Regasification Unit From BW LNG To Contribute To Italy's Energy Security And Diversification] | # [https://lng-news.blogspot.com/2022/07/snam-purchases-new-floating.html Snam Purchases New Floating Regasification Unit From BW LNG To Contribute To Italy's Energy Security And Diversification] | ||
+ | # [https://lng-news.blogspot.com/2023/09/corinth-pipeworks-was-awarded-contract.html Corinth Pipeworks was awarded contract for the Floating Storage and Regasification Unit (FSRU) pipeline in Italy] | ||
[[category:LNG]] | [[category:LNG]] | ||
[[category:Italy]] | [[category:Italy]] | ||
[[category:Snam]] | [[category:Snam]] |
Revision as of 10:58, 27 September 2023
Contents
Summary Information
- Ownership: Snam
- Website: https://www.snam.it/
- Location: Northern Italy
- Capacity: 5 BCM/annum
- Status: Planned
Brief Description
- BW Singapore, built in 2015, has a maximum storage capacity of about 170,000 cubic metres of LNG (liquefied natural gas) and a nominal continuous regasification capacity of about 5 billion cubic metres per year.
Technical Details
- Storage capacity: 170,000 cubic metres
- Unloading capacity:
- Send out capacity: 5BCM/annum
- Constructor:
- Corinth Pipeworks: manufacture and supply approximately 13 km of longitudinally submerged arc-welded steel pipes
Ongoing Projects/Project Status
- The vessel is contracted until the second half of 2023, after which it will be transferred to Snam
- The project is scheduled for completion in late 2023
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2022 - Snam acquired the vessel from BW LNG
Other Information
-