+++ Description
- Siri and Stine segment 2 (SCA) comprise a combined wellhead, processing and accommodation platform.
- The processing facilities consist of a plant that separates the hydrocarbons produced and a plant for processing the water produced. The platform also houses equipment for co-injecting gas and water.
- Stine segment 1 (SCB) is developed as a satellite to the Siri platform and consists of two subsea installations with a production well and an injection well.
- Production from SCB is conveyed to the Siri platform for processing.
- The Siri platform also supplies injection water and lift gas to the satellite installations at SCB, Nini and [[[Cecilie Oil Field | Cecilie]]]. Injection water is supplied to SCB via a branch of the water pipeline leading to Nini.
- The oil produced is piped to a 50,000 m³ storage tank on the seabed, and subsequently transferred to a tanker by means of buoy-loading facilities.
+++ Contractors
- **Wilton Engineering:** Fabricating large caisson clamps
- **Aker Maritime:** Siri Storage Tank
+++ History
- 1995 - Siri Oil Field discovered
- 1999 - First production
- 2005 - Talisman acquires Paladin, getting a stake the field
- 2009 - DONG Energy decided to stop production from the Siri platform. The decision was effectuated after a routine inspection revealing cracks in a subsea structure connected to the oil storage tank below the Siri platform
- 2011 - Noreco sold its share of the field to DONG
- 2017 - Ineos acquired a stake from DONG
+++ Geology
- The Siri Field is a structural trap with a Paleocene sandstone reservoir. The accumulation consists of oil with a relatively low content of gas.
+++ Links
- Appendix B: Producing fields, ENS, 2008 Report
- [[[FoundOcean Europe Subsea References]]]
- Talisman to Acquire Paladin Resources Plc for Pounds Sterling 1,218 Million 'C$2,521 Million'
- Temporary stop of production on the Siri-platform
- Sale of Siri field completed
- Wilton Engineering Secures Major North Sea Project with Subsea 7