Line 11: | Line 11: | ||
* Binhai LNG facility includes one jetty to accommodate 125,000-266,000 cubic meter LNG carrier and four 220,000 cubic meters LNG tanks | * Binhai LNG facility includes one jetty to accommodate 125,000-266,000 cubic meter LNG carrier and four 220,000 cubic meters LNG tanks | ||
− | + | === Technical Details === | |
* Storage capacity: four 160,000 m3 LNG storage tanks | * Storage capacity: four 160,000 m3 LNG storage tanks | ||
* Unloading capacity: | * Unloading capacity: | ||
Line 20: | Line 20: | ||
− | + | === Ongoing Projects/Project Status === | |
− | * | + | * The terminal was commissioned in [[LNG Terminal Projects Completed in 2015 | 2015]] |
+ | * An expansion is underway which should be completed in 2023 | ||
− | + | === Suppliers / Customers === | |
* Suppliers: | * Suppliers: | ||
* Customers: | * Customers: | ||
− | + | === History === | |
* 2012 - The National Development and Reform Commission approved construction of the terminal | * 2012 - The National Development and Reform Commission approved construction of the terminal | ||
− | + | === Other Information === | |
* - | * - | ||
=== Links === | === Links === | ||
# [http://killajoules.wikidot.com/blog:2894 Approval of CNOOC's Shenzhen Diefu liquefied natural gas project] | # [http://killajoules.wikidot.com/blog:2894 Approval of CNOOC's Shenzhen Diefu liquefied natural gas project] |
Revision as of 12:15, 7 January 2022
Contents
Summary Information
- Ownership: CNOOC
- Website: http://www.cnoocgas.com/
- Location:
- Capacity: 4.0 million tons/annum
- Status: Planned
Brief Description
- Binhai LNG facility includes one jetty to accommodate 125,000-266,000 cubic meter LNG carrier and four 220,000 cubic meters LNG tanks
Technical Details
- Storage capacity: four 160,000 m3 LNG storage tanks
- Unloading capacity:
- Send out capacity:
- Constructor:
- TGE and Sinopec Ningbo Engineering Co: Turn-key project of four LNG full-capacity tanks
Ongoing Projects/Project Status
- The terminal was commissioned in 2015
- An expansion is underway which should be completed in 2023
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2012 - The National Development and Reform Commission approved construction of the terminal