Summary Information
- Ownership: BW Gas and InterEnergy Holdings
- Website: http://www.bwgas.com/
- Location: Dominican Republic
- Capacity: million tons/annum
- Status: Planned
+++ Brief Description
- A small single tanked regasification unit
+++ Technical Details
- Storage capacity: 1 Tank - 160,000 cubic meters
- Unloading capacity:
- Send out capacity: 240 million standard cubic feet per day (MMscf/d)
- Constructor: Foster Wheeler AG was awarded the basic design and front-end engineering design contract
- Licensor:
+++ Ongoing Projects/Project Status
- Commissioning is expected in [[[LNG Terminals to be Completed in 2014 | 2014]]]
+++ Suppliers / Customers
- Suppliers:
- Customers: InterEnergy's power plants
+++ History
- 2011 - BW Gas and InterEnergy Holdings announce the project
- 2012 - Foster Wheeler AG has been awarded the basic design and front-end engineering design contract
+++ Other Information
- The project is expected to cost US$350 million
- The design will also consider future expansion(s) up to 700 MMscf/d