San Pedro de Macoris LNG Terminal

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Ownership: BW Gas and InterEnergy Holdings
  • Website: http://www.bwgas.com/
  • Location: Dominican Republic
  • Capacity: million tons/annum
  • Status: Planned

+++ Brief Description

  • A small single tanked regasification unit

+++ Technical Details

  • Storage capacity: 1 Tank - 160,000 cubic meters
  • Unloading capacity:
  • Send out capacity: 240 million standard cubic feet per day (MMscf/d)
  • Constructor: Foster Wheeler AG was awarded the basic design and front-end engineering design contract
  • Licensor:


+++ Ongoing Projects/Project Status

  • Commissioning is expected in [[[LNG Terminals to be Completed in 2014 | 2014]]]

+++ Suppliers / Customers

  • Suppliers:
  • Customers: InterEnergy's power plants


+++ History

  • 2011 - BW Gas and InterEnergy Holdings announce the project
  • 2012 - Foster Wheeler AG has been awarded the basic design and front-end engineering design contract

+++ Other Information

  • The project is expected to cost US$350 million
  • The design will also consider future expansion(s) up to 700 MMscf/d

+++ Relevant Links

  1. BW Gas and InterEnergy Holdings join forces in new gas venture in the Dominican Republic
  2. Foster Wheeler Awarded Contract for an LNG Receiving Terminal in Dominican Republic