Difference between revisions of "Revithoussa LNG Terminal"
Abarrelfull (talk | contribs) (→Links) |
Abarrelfull (talk | contribs) |
||
Line 1: | Line 1: | ||
− | Summary Information | + | === Summary Information === |
Ownership: DEPA | Ownership: DEPA | ||
Line 6: | Line 6: | ||
Capacity: 2.0 million tons/annum | Capacity: 2.0 million tons/annum | ||
Status: In Operation | Status: In Operation | ||
− | Technical Details | + | === Technical Details === |
Storage capacity: 2 tanks of 65.000 m3 LNG useful volume. | Storage capacity: 2 tanks of 65.000 m3 LNG useful volume. | ||
Line 14: | Line 14: | ||
407 m3 LNG/hour or 2,1 bcma (Peak with 1 vaporizer as spare). | 407 m3 LNG/hour or 2,1 bcma (Peak with 1 vaporizer as spare). | ||
533 m3 LNG/hour or 2,5 bcma (Full S.R. without spare). | 533 m3 LNG/hour or 2,5 bcma (Full S.R. without spare). | ||
− | History | + | === History === |
2000 - The terminal recieves its first cargo | 2000 - The terminal recieves its first cargo | ||
2007 - Terminal Expanded | 2007 - Terminal Expanded | ||
2012 - Tender launched for third tank | 2012 - Tender launched for third tank | ||
− | Ongoing Projects/Project Status | + | === Ongoing Projects/Project Status === |
A second expansion is under study comprising one additional third LNG tank, one additional truck loading facilities and an increase of the send-out capacity | A second expansion is under study comprising one additional third LNG tank, one additional truck loading facilities and an increase of the send-out capacity | ||
A tender has been launched for the expansion | A tender has been launched for the expansion | ||
− | Suppliers / Customers | + | === Suppliers / Customers === |
Suppliers: Algeria, Sonatrach | Suppliers: Algeria, Sonatrach | ||
Customers: | Customers: | ||
− | Other Information | + | === Other Information === |
The terminal was built by Sofregaz & Preliminary engineering studies were performed by Tractebel | The terminal was built by Sofregaz & Preliminary engineering studies were performed by Tractebel |
Revision as of 10:04, 21 August 2020
Contents
Summary Information
Ownership: DEPA Website: http://www.depa.gr/ Location: Revithoussa Island, Megara Bay – Attica – GREECE Capacity: 2.0 million tons/annum Status: In Operation
Technical Details
Storage capacity: 2 tanks of 65.000 m3 LNG useful volume. Unloading capacity: 3.500 m3 LNG / hour. Send out capacity: 270 m3 LNG/hour or 1,4 bcma (S.M.S.R.). 407 m3 LNG/hour or 2,1 bcma (Peak with 1 vaporizer as spare). 533 m3 LNG/hour or 2,5 bcma (Full S.R. without spare).
History
2000 - The terminal recieves its first cargo 2007 - Terminal Expanded 2012 - Tender launched for third tank
Ongoing Projects/Project Status
A second expansion is under study comprising one additional third LNG tank, one additional truck loading facilities and an increase of the send-out capacity A tender has been launched for the expansion
Suppliers / Customers
Suppliers: Algeria, Sonatrach Customers:
Other Information
The terminal was built by Sofregaz & Preliminary engineering studies were performed by Tractebel
Links
- Terminal Webpage
- Revithoussa LNG Terminal Presentation
- REVITHOUSSA - GREECE - LNG IMPORT TERMINAL - SECOND EXTENSION
- Tractebel Engineering LNG References
- Saipem LNG References
- EGL Delivers First LNG Cargo To Greece
- Notice For an international tender for design and construction of a new LNG Tank in Revithoussa
- The Snam, Enagás, Fluxys consortium awarded the tender for the acquisition of 66% of the Greek operator DESFA