Oyong Oil and Gas Field
Jump to navigation
Jump to search
Summary Information
- Operator: Santos
- Country: Indonesia
- Location: 2.19 - Sampang PSC, Madura Island, East Java
- Production start: 2007
- Partners:
- Type: Oil & Gas
- Estimated Reserves:
- Production Volume:
+++ Description
- The field has had an offshore wellhead platform installed with five oil and two gas production wells.
- Oil processing is undertaken on the Sea Good 101 production barge and then piped to the Shanghai FSO for storage and offtake
- Oyong Phase-2 involved modifications to the offshore facilities and construction of a 60-kilometre pipeline to a new onshore gas processing facility located in East Java
- The development includes the satellite field Wortel
- The Wortel development includes two gas wells, an unmanned wellhead platform and a 10-kilometre gas pipeline to the Oyong Field
+++ Contractors
- **Icon Engineering:** conceptual engineering, multi-discipline detailed design and installation engineering for the Oyong wellhead platform
+++ History
- 2001 - Oyong Oil And Gas Field discovered
- 2003 - Gas sales contact signed
- 2005 - Development approval granted from Government
- 2007 - Oyong commenced oil production
- 2009 - Oyong commenced gas production
- 2010 - Wortel project approved for development
- 2012 - Production commenced from Wortel
+++ Geology