* Operator: Petronas | * Operator: Petronas | ||
* Country: Turkmenistan | * Country: Turkmenistan | ||
− | * Location: Caspian Sea | + | * Location: Block 1, Caspian Sea |
* Production start: 2006 | * Production start: 2006 | ||
* Partners: | * Partners: | ||
Line 10: | Line 10: | ||
+++ Description | +++ Description | ||
− | * The field utilises | + | * The field utilises two wellhead / riser platforms and the FSO Oguzhan. Gas is transported to an onshore terminal |
+++ Contractors | +++ Contractors | ||
+ | * '''Technip / MMHE:''' Pre-FEED, FEED and EPCI for two wellhead / riser platforms and an onshore gas terminal. | ||
* '''MMHE:''' MCR-A - Jacket, Deck, Heli-deck, Topside | * '''MMHE:''' MCR-A - Jacket, Deck, Heli-deck, Topside | ||
* '''Ilk Insaat:''' | * '''Ilk Insaat:''' | ||
Line 19: | Line 20: | ||
+++ History | +++ History | ||
+ | * 2004 - Technip / MMHE awarded Pre-FEED for project | ||
* 2006 - Production started | * 2006 - Production started | ||
* 2009 - Petronas acquired the Platform and FSO | * 2009 - Petronas acquired the Platform and FSO |
Latest revision as of 10:36, 22 February 2024
Summary Information
- Operator: Petronas
- Country: Turkmenistan
- Location: Block 1, Caspian Sea
- Production start: 2006
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
+++ Description
- The field utilises two wellhead / riser platforms and the FSO Oguzhan. Gas is transported to an onshore terminal
+++ Contractors
- Technip / MMHE: Pre-FEED, FEED and EPCI for two wellhead / riser platforms and an onshore gas terminal.
- MMHE: MCR-A - Jacket, Deck, Heli-deck, Topside
- Ilk Insaat:
- Procurement, fabrication, Integration of Collector Riser Platform.
- Drilling Platform-A Project - Temporary construction facilities, earthworks, engineering and design, fabrication, E&I, topside integration, jackets integration, pile fabrication
+++ History
- 2004 - Technip / MMHE awarded Pre-FEED for project
- 2006 - Production started
- 2009 - Petronas acquired the Platform and FSO
+++ Geology
+++ Links