Difference between revisions of "Macedon Gas Field"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 9: | Line 9: | ||
* Production Volume: | * Production Volume: | ||
− | === Description | + | === Description === |
* Macedon gas development consists of four wells in approximately 180 meters (590 feet) water depth | * Macedon gas development consists of four wells in approximately 180 meters (590 feet) water depth | ||
* Recoverable reserves for the Macedon field are between 400 and 750 billion cubic feet of gas. | * Recoverable reserves for the Macedon field are between 400 and 750 billion cubic feet of gas. | ||
Line 15: | Line 15: | ||
* A sales gas pipeline will be connected to the [[Dampier to Bunbury Natural Gas Pipeline]] for sale to the domestic gas market in Western Australia | * A sales gas pipeline will be connected to the [[Dampier to Bunbury Natural Gas Pipeline]] for sale to the domestic gas market in Western Australia | ||
− | === Contractors | + | === Contractors === |
* **McDermott:** EPCI - 20-inch pipeline, 8-inch main umbilical, infield umbilicals, flexible flowlines & associated subsea structures, MUTA, SUTAs, etc.), rigid jumpers, flying leads | * **McDermott:** EPCI - 20-inch pipeline, 8-inch main umbilical, infield umbilicals, flexible flowlines & associated subsea structures, MUTA, SUTAs, etc.), rigid jumpers, flying leads | ||
* **Oceaneering :** 100 km (62 miles) of steel tube umbilicals and associated distribution equipment, including termination assemblies and flying leads | * **Oceaneering :** 100 km (62 miles) of steel tube umbilicals and associated distribution equipment, including termination assemblies and flying leads | ||
Line 25: | Line 25: | ||
** 1 x Induced Gas Flotation Unit | ** 1 x Induced Gas Flotation Unit | ||
− | === History | + | === History === |
* 1992 - Macedon field discovered | * 1992 - Macedon field discovered | ||
* 2010 - BHP Billiton Approves Macedon Gas Development | * 2010 - BHP Billiton Approves Macedon Gas Development | ||
Line 36: | Line 36: | ||
* 2022 - Woodside becomes operator after BHP Billiton merger | * 2022 - Woodside becomes operator after BHP Billiton merger | ||
− | === Geology | + | === Geology === |
* | * | ||
− | === Links | + | === Links === |
# [[McDermott Platform References]] | # [[McDermott Platform References]] | ||
# [[Process Group Oil And Gas Processing References]] | # [[Process Group Oil And Gas Processing References]] |
Latest revision as of 07:56, 29 November 2023
Summary Information
- Operator: Woodside
- Country: Australia
- Location: 17 kilometers off Onslow in North West Australia
- Production start: 2013
- Partners: Woodside - 71.43%, Santos - 28.57%
- Type: Gas
- Estimated Reserves: 400 and 750 billion cubic feet of gas
- Production Volume:
Description
- Macedon gas development consists of four wells in approximately 180 meters (590 feet) water depth
- Recoverable reserves for the Macedon field are between 400 and 750 billion cubic feet of gas.
- Project costs will be approximately US$1.5 billion
- A sales gas pipeline will be connected to the Dampier to Bunbury Natural Gas Pipeline for sale to the domestic gas market in Western Australia
Contractors
- **McDermott:** EPCI - 20-inch pipeline, 8-inch main umbilical, infield umbilicals, flexible flowlines & associated subsea structures, MUTA, SUTAs, etc.), rigid jumpers, flying leads
- **Oceaneering :** 100 km (62 miles) of steel tube umbilicals and associated distribution equipment, including termination assemblies and flying leads
- **Technip:** Onshore facilities consisting of a gas plant and pipelines works
- **STREICHER-Clough:** Pipeline construction work - horizontal directional drilling, construction of an onshore wet gas pipeline and sales gas pipeline and umbilical installation
- **Axens:** Mercury removal unit
- **Process Group:** Water Treatment Package
- 1 x Corrugated Plate Interceptor
- 1 x Induced Gas Flotation Unit
History
- 1992 - Macedon field discovered
- 2010 - BHP Billiton Approves Macedon Gas Development
- 2010 - Oceaneering awarded umbilicals contract
- 2011 - Technip awarded contract for onshore facilities
- 2011 - STREICHER-Clough awarded pipeline contract
- 2013 - First gas produced
- 2015 - Quandrant Energy acquired Apache's share
- 2018 - Santos acquired Quadrant Energy
- 2022 - Woodside becomes operator after BHP Billiton merger
Geology
Links
- McDermott Platform References
- Process Group Oil And Gas Processing References
- Oceaneering Announces BHP Billiton Umbilical and Distribution Equipment Contract
- Technip awarded contract for onshore gas project in Australia
- STREICHER–Clough Joint Venture awarded new contract
- BHP Billiton Approves Macedon Gas Development In Western Australia
- BHP Billiton Celebrates First Gas at Macedon
- Axens’ Mercury Removal Products Selected for Macedon
- Apache Agrees To Sell Australian Operations For $2.1 Billion
- Santos announced today the acquisition of 100% of Quadrant Energy
- Woodside Completes Merger with BHP Petroleum