* We only expect 2 new export terminals to enter operation in 2022, bringing 7.2 million tons of capacity
 
* We only expect 2 new export terminals to enter operation in 2022, bringing 7.2 million tons of capacity
 +
* There will be a very significant expansion of import capacity however, totalling about 45 mn tons
  
 
==== Export Terminals ====
 
==== Export Terminals ====

Revision as of 14:53, 18 January 2022

Introduction

  • We only expect 2 new export terminals to enter operation in 2022, bringing 7.2 million tons of capacity
  • There will be a very significant expansion of import capacity however, totalling about 45 mn tons

Export Terminals

  1. Tangguh LNG Terminal Expansion
  2. Coral South LNG Project

Import Terminals

  1. Barcarena LNG Terminal - Brazil
  2. Cyprus LNG Terminal - Cyprus
  3. Dhamra LNG Terminal - India
  4. Hong Kong LNG Terminal - Hong Kong
  5. Luzon LNG Terminal - Philippines
  6. Suape LNG Terminal - Brazil
  7. ThiVai LNG Receiving terminal - Vietnam
  8. Wenzhou LNG Terminal - China