=== Description === | === Description === | ||
* In order to access the new reservoir, the project has installed a new subsea system and caisson onto the [[Andrew Oil and Gas Field | Andrew platform]]. Four subsea pipeline bundles with a total length of 28 km - the longest bundle system in the world - will carry the fluids to the Andrew platform for processing and onward export. | * In order to access the new reservoir, the project has installed a new subsea system and caisson onto the [[Andrew Oil and Gas Field | Andrew platform]]. Four subsea pipeline bundles with a total length of 28 km - the longest bundle system in the world - will carry the fluids to the Andrew platform for processing and onward export. | ||
− | * Production from Kinnoull is forecast to peak at 45,000 barrels per day and be exported via the existing [[Forties Pipeline System]] to Kinneil and the [[ | + | * Production from Kinnoull is forecast to peak at 45,000 barrels per day and be exported via the existing [[Forties Pipeline System]] to Kinneil and the [[CATS Central Area Transmission System Gas Pipeline | CATS]] pipeline system to Teesside. |
* The Arundel field is tied into the Kinnoull infrastructure | * The Arundel field is tied into the Kinnoull infrastructure | ||
Latest revision as of 07:50, 31 January 2024
Summary Information
- Operator: BP
- Country: UK
- Location: central North Sea
- Production start: 2014
- Partners: BP - 77.06%, Eni - 16.67%; JX Nippon - 6.27%
- Type: Oil & Gas
- Estimated Reserves:
- Production Volume:
Description
- In order to access the new reservoir, the project has installed a new subsea system and caisson onto the Andrew platform. Four subsea pipeline bundles with a total length of 28 km - the longest bundle system in the world - will carry the fluids to the Andrew platform for processing and onward export.
- Production from Kinnoull is forecast to peak at 45,000 barrels per day and be exported via the existing Forties Pipeline System to Kinneil and the CATS pipeline system to Teesside.
- The Arundel field is tied into the Kinnoull infrastructure
Contractors
- **Heerema:** fabrication of the 750 tons process module with a length 18 meters, a width of 13 meters and a height of 28 meters for installation on the existing BP Andrew platform
- **Subsea 7:** Engineer, procure, fabricate, install and commission a 28km pipeline bundle system consisting of production, gas lift and methanol pipelines. Also included is the installation of a 28km electro-hydraulic control umbilical, tie-ins of integrated subsea towhead structures, field testing and pre-commissioning works.
History
- 2008 - The Kinnoull Oil And Gas Field is discovered
- 2010 - Subsea 7 awarded Major Pipeline Bundle Contract
- 2011 - BP and Co-Venturers Approve Development of Kinnoull Field
- 2012 - Nippon Oil increased its stake in the field
- 2012 - The new 700 tonne processing unit for the Kinnoull and Andrew Lower Cretaceous reservoirs, was successfully installed on to BP’s Andrew platform
- 2012 - JX Nippon acquires an additional stake from ENI
- 2014 - First oil produced
- 2016 - Approval for Arundel field
Geology
Links
- UK Oil and Gas Fields by Approval Date
- Eni makes a new oil discovery in the UK North Sea
- Subsea 7 Announces Major Pipeline Bundle Contract for BP in the North Sea
- BP and Co-Venturers Approve Development of Kinnoull Field
- Exchange of Pierce field and Kinnoull field in UK North Sea
- BP Announces Completion of Major Milestone on Kinnoull Project in UK’s Central North Sea
- Major asset acquisition in the UKCS
- Loan for Acquisition of Interests and Development of Oil Fields in British North Sea
- First oil from the Kinnoull field in the UK North Sea