Khazzan Gas Field

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Operator: BP
  • Country: Oman
  • Location: Block 61
  • Production start: Expected 2017
  • Partners:
  • Type: Gas
  • Estimated Reserves:
  • Production Volume:

+++ Description

  • The Khazzan project represents the first phase in the development of one of the Middle East region’s largest unconventional tight gas accumulations. Owing to the tight nature of rocks in Khazzan reservoirs, the wells need to be hydraulically stimulated to stimulate production and flow gas at target rates.
  • The full field development will involve a drilling programme of around 300 wells over 15 years to deliver plateau production of one billion cubic feet (28.3 million cubic metres) of gas per day and 25,000 barrels per day of gas condensate.
  • The CPF will include two process trains, each having a capacity of 525 million standard cubic feet of gas per day.
  • The project also includes an associated condensate processing system, power generation plant, water treatment system and all associated utilities and infrastructure

+++ Contractors

  • **Petrofac:** Engineering, procurement and construction (EPC) of the central processing facility (CPF)
  • **Jacobs:** Engineering, procurement and construction management services in relation to approximately $2 billion of gas gathering and water pipelines, wellhead production facilities and export pipelines
  • **Global Geophysical Services:** Contract for seismic acquisition
  • **PGS Data Processing:** Processing of the new seismic and re-processing of the existing seismic data
  • **Worley Parsons:** Select stage engineering including evaluation of options for the appraisal phase of early production
  • **Dalma Energy & Co:** Drilling contract

+++ History

  • 1993 - Khazzan Gas Field discovered
  • 2007 - BP signed an agreement for the appraisal and development of Block 61
  • 2008 - BP began appraisal well drilling activities
  • 2013 - The Government of the Sultanate of Oman and BP announced a gas sales agreement and an amended production sharing agreement
  • 2014 - EPC contracts awarded

+++ Geology

  • Owing to the tight nature of rocks in Khazzan reservoirs, the wells need to be hydraulically stimulated

+++ Links

  1. BP Signs Oman Deal Which Could Yield Some 20 - 30 Trillion Cubic Feet of Gas
  2. BP Awards First Phase Oman Appraisal Contracts
  3. The Government of the Sultanate of Oman Gives the Go-Ahead to BP for the Khazzan Project
  4. Petrofac awarded Khazzan CPF project in Sultanate of Oman
  5. Jacobs Awarded Contract by BP Supporting Development of Khazzan Gas Project