=== Description === | === Description === | ||
− | * The Juniper facility takes gas from the | + | * The Juniper facility takes gas from the '''Corallita''' and '''Lantana''' fields located 50 miles off the south east coast of Trinidad in water-depth of approximately 360 feet |
* The development consists of a normally unmanned platform together with corresponding subsea infrastructure | * The development consists of a normally unmanned platform together with corresponding subsea infrastructure | ||
* It includes five subsea wells and has a production capacity of approximately 590 million standard cubic feet a day (mmscfd). | * It includes five subsea wells and has a production capacity of approximately 590 million standard cubic feet a day (mmscfd). | ||
− | * Gas from Juniper flows to the Mahogany B hub via a ten kilometre flowline | + | * Gas from Juniper flows to the [[Mahogany Gas Field | Mahogany B hub]] via a ten kilometre flowline |
==== Cypre ==== | ==== Cypre ==== | ||
* The Cypre gas field is located 78 kilometres off the southeast coast of Trinidad within the East Mayaro Block, in water depth of approximately 80 metres. | * The Cypre gas field is located 78 kilometres off the southeast coast of Trinidad within the East Mayaro Block, in water depth of approximately 80 metres. | ||
Line 33: | Line 33: | ||
* 2017 - First gas produced | * 2017 - First gas produced | ||
* 2018 - FID for the Matapal Compression project | * 2018 - FID for the Matapal Compression project | ||
+ | * 2021 - First gas from Matapal | ||
* 2022 - FID for Cypre development | * 2022 - FID for Cypre development | ||
Line 44: | Line 45: | ||
# [https://abarrelfull.blogspot.com/2022/11/bp-begins-production-from-juniper.html BP begins production from Juniper project in Trinidad] | # [https://abarrelfull.blogspot.com/2022/11/bp-begins-production-from-juniper.html BP begins production from Juniper project in Trinidad] | ||
# [https://abarrelfull.blogspot.com/2024/02/bp-announces-sanction-of-cassia.html BP announces sanction of Cassia Compression and Matapal gas projects in Trinidad] | # [https://abarrelfull.blogspot.com/2024/02/bp-announces-sanction-of-cassia.html BP announces sanction of Cassia Compression and Matapal gas projects in Trinidad] | ||
+ | # [https://abarrelfull.blogspot.com/2024/02/trinidads-matapal-achieves-early-first.html Trinidad’s Matapal achieves early first gas | ||
+ | February 21, 2024] | ||
# [https://abarrelfull.blogspot.com/2022/11/cypre-project-gets-go-ahead.html Cypre project gets go ahead] | # [https://abarrelfull.blogspot.com/2022/11/cypre-project-gets-go-ahead.html Cypre project gets go ahead] | ||
# [https://a-barrel-full.blogspot.com/2022/11/subsea7-awarded-contract-offshore.html Subsea7 awarded contract offshore Trinidad and Tobago] | # [https://a-barrel-full.blogspot.com/2022/11/subsea7-awarded-contract-offshore.html Subsea7 awarded contract offshore Trinidad and Tobago] |
Revision as of 08:22, 21 February 2024
Contents
Summary Information
- Operator: BP
- Country: Trinidad and Tobago
- Location: 50 miles off the south east coast of Trinidad
- Production start: 2017
- Partners:
- Type: Gas
- Estimated Reserves:
- Production Volume: 590 million standard cubic feet a day (mmscfd) - est.
Description
- The Juniper facility takes gas from the Corallita and Lantana fields located 50 miles off the south east coast of Trinidad in water-depth of approximately 360 feet
- The development consists of a normally unmanned platform together with corresponding subsea infrastructure
- It includes five subsea wells and has a production capacity of approximately 590 million standard cubic feet a day (mmscfd).
- Gas from Juniper flows to the Mahogany B hub via a ten kilometre flowline
Cypre
- The Cypre gas field is located 78 kilometres off the southeast coast of Trinidad within the East Mayaro Block, in water depth of approximately 80 metres.
- Cypre will include seven wells and subsea trees tied back into the existing Juniper platform via two new 14 kilometre flexible flowlines.
- At its peak, the development is expected to deliver average gas production of 250-300 million standard cubic feet a day (mmscfd).
Matapal
- The Matapal project developed the gas resources discovered by BPTT in 2017 with the Savannah exploration well. The project is a three-well subsea tie-back to the Juniper platform
Contractors
- Technip: design, detailed engineering, procurement, construction, load out and mechanical completion of topsides, jacket, flowlines, subsea structures and tie-in spools
- Gulf Marine Fabricators: Construction of the jacket and piles
- TOFCO: Construction of the platform topsides
Cypre
- Subsea 7: concept and design, engineering, procurement, construction and installation of a two-phase liquid natural gas tieback to the Juniper platform through dual flexible flowlines and a manifold gathering system, along with topside upgrades.
History
- 2012 - Front End Engineering and Design (FEED) launched
- 2014 - Final investment decision made
- 2017 - First gas produced
- 2018 - FID for the Matapal Compression project
- 2021 - First gas from Matapal
- 2022 - FID for Cypre development
Geology
Links
- BPTT ‘s Juniper Project Gets go Ahead
- Technip awarded a substantial EPIC contract for the Juniper field offshore Trinidad
- BP’s Juniper platform sets sail for offshore Trinidad
- BP begins production from Juniper project in Trinidad
- BP announces sanction of Cassia Compression and Matapal gas projects in Trinidad
- [https://abarrelfull.blogspot.com/2024/02/trinidads-matapal-achieves-early-first.html Trinidad’s Matapal achieves early first gas
February 21, 2024]