Juniper Offshore Gas Fields

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Operator: BP
  • Country: Trinidad and Tobago
  • Location: 50 miles off the south east coast of Trinidad
  • Production start: 2017
  • Partners:
  • Type: Gas
  • Estimated Reserves:
  • Production Volume: 590 million standard cubic feet a day (mmscfd) - est.

Description

  • The Juniper facility takes gas from the Corallita and Lantana fields located 50 miles off the south east coast of Trinidad in water-depth of approximately 360 feet
  • The development consists of a normally unmanned platform together with corresponding subsea infrastructure
  • It includes five subsea wells and has a production capacity of approximately 590 million standard cubic feet a day (mmscfd).
  • Gas from Juniper flows to the Mahogany B hub via a ten kilometre flowline

Cypre

  • The Cypre gas field is located 78 kilometres off the southeast coast of Trinidad within the East Mayaro Block, in water depth of approximately 80 metres.
  • Cypre will include seven wells and subsea trees tied back into the existing Juniper platform via two new 14 kilometre flexible flowlines.
  • At its peak, the development is expected to deliver average gas production of 250-300 million standard cubic feet a day (mmscfd).

Matapal

  • The Matapal project developed the gas resources discovered by BPTT in 2017 with the Savannah exploration well. The project is a three-well subsea tie-back to the Juniper platform

Contractors

  • Technip: design, detailed engineering, procurement, construction, load out and mechanical completion of topsides, jacket, flowlines, subsea structures and tie-in spools
  • Gulf Marine Fabricators: Construction of the jacket and piles
  • TOFCO: Construction of the platform topsides

Cypre

  • Subsea 7: concept and design, engineering, procurement, construction and installation of a two-phase liquid natural gas tieback to the Juniper platform through dual flexible flowlines and a manifold gathering system, along with topside upgrades.

History

  • 2012 - Front End Engineering and Design (FEED) launched
  • 2014 - Final investment decision made
  • 2017 - First gas produced
  • 2018 - FID for the Matapal Compression project
  • 2021 - First gas from Matapal
  • 2022 - FID for Cypre development

Geology

Links

  1. BPTT ‘s Juniper Project Gets go Ahead
  2. Technip awarded a substantial EPIC contract for the Juniper field offshore Trinidad
  3. BP’s Juniper platform sets sail for offshore Trinidad
  4. BP begins production from Juniper project in Trinidad
  5. BP announces sanction of Cassia Compression and Matapal gas projects in Trinidad
  6. Trinidad’s Matapal achieves early first gas
  7. Cypre project gets go ahead
  8. Subsea7 awarded contract offshore Trinidad and Tobago