Line 20: | Line 20: | ||
* **Alfa Laval:** Condensate preheaters | * **Alfa Laval:** Condensate preheaters | ||
* **Process Group:** | * **Process Group:** | ||
− | + | ** Fuel Gas H2S and Mercury Removal Package | |
− | + | ** 3 x 672 MMSCFD TEG Dehydration Packages | |
+++ Status | +++ Status | ||
* Under construction | * Under construction | ||
− | + | === History === | |
* 2012 - Technip awarded topsides contract | * 2012 - Technip awarded topsides contract | ||
* 2013 - Construction started | * 2013 - Construction started | ||
Line 32: | Line 32: | ||
* 2014 - Keel laying ceremony held | * 2014 - Keel laying ceremony held | ||
* 2015 - Topsides integration started | * 2015 - Topsides integration started | ||
+ | * 2018 - First gas production | ||
Revision as of 17:58, 14 November 2020
Summary Information
- Name: Ichthys FPSO
- Field: Ichthys Gas Field
- Country: Australia
- Ownership: Inpex
- Website: http://www.inpex.co.jp/
- Operated By: Inpex
- Capacity: 100,000 bpd
- Year of Completion
Brief Description
- The FPSO is part of the [[[Ichthys LNG Terminal | Ichthys LNG Project]]]. The vessel will be used for condensate dewatering, stabilisation, storage and export
- The vessel will be 336m by 59m and has production capacity of 100,000 barrels of gas condensate per day and 1.2 million barrels storage capacity
Contractors
- **Daewoo Shipbuilding & Marine Engineering (DSME):** Construction of FPSO hull
- **Technip:** Detailed engineering and procurement assistance for the topsides facilities
- **Alfa Laval:** Condensate preheaters
- **Process Group:**
- Fuel Gas H2S and Mercury Removal Package
- 3 x 672 MMSCFD TEG Dehydration Packages
+++ Status
- Under construction
History
- 2012 - Technip awarded topsides contract
- 2013 - Construction started
- 2013 - Alfa Laval awarded heater contract
- 2014 - Keel laying ceremony held
- 2015 - Topsides integration started
- 2018 - First gas production
+++ Other Information
- -
Links
- [[[Process Group Oil And Gas Processing References]]]
- Technip awarded contract for Ichthys FPSO unit
- Construction begins on last major offshore facility (FPSO) for Ichthys
- Alfa Laval wins SEK 130 million offshore gas order in South Korea
- Ichthys LNG Project Celebrates FPSO Keel Laying
- Ichthys topsides integration starts with lifts
INPEX-operated Ichthys LNG Project Commences Production