Ichthys FPSO

From A Barrel Full
Jump to navigation Jump to search

Summary Information

Brief Description

  • The FPSO is part of the Ichthys LNG Terminal. The vessel will be used for condensate dewatering, stabilisation, storage and export
  • The vessel will be 336m by 59m and has production capacity of 100,000 barrels of gas condensate per day and 1.2 million barrels storage capacity

Contractors

  • Daewoo Shipbuilding & Marine Engineering (DSME): Construction of FPSO hull
  • **Technip:** Detailed engineering and procurement assistance for the topsides facilities
  • **Alfa Laval:** Condensate preheaters
  • **Process Group:**
    • Fuel Gas H2S and Mercury Removal Package
    • 3 x 672 MMSCFD TEG Dehydration Packages
  • Wärtsilä: supply of inert gas generator units

Status

  • In operation

History

  • 2012 - Technip awarded topsides contract
  • 2013 - Construction started
  • 2013 - Alfa Laval awarded heater contract
  • 2014 - Keel laying ceremony held
  • 2015 - Topsides integration started
  • 2018 - First gas production


Other Information

  • -

Links

  1. Process Group Oil And Gas Processing References
  2. Wärtsilä FPSO References
  3. Technip awarded contract for Ichthys FPSO unit
  4. Construction begins on last major offshore facility (FPSO) for Ichthys
  5. Alfa Laval wins SEK 130 million offshore gas order in South Korea
  6. Ichthys LNG Project Celebrates FPSO Keel Laying
  7. Ichthys topsides integration starts with lifts
  8. INPEX-operated Ichthys LNG Project Celebrates Startup of Operations