Summary Information

  • Ownership: First Gen
  • Website: https://www.firstgen.com.ph/
  • Location: Batangas, Philippines
  • Capacity: million tons/annum
  • Status: Under construction

Brief Description

  • A floating regasification unit that utilises the vessel BW Paris

Technical Details

  • Storage capacity:
  • Unloading capacity:
  • Send out capacity:
  • Constructor:
    • Keppel: FRSU conversion
    • McConnell Dowell: Engineering, Procurement and Construction of both the Multiple Purpose Jetty and Onshore Gas Receiving Facility.

Ongoing Projects/Project Status

  • The terminal is to be commissioned in 2023

Suppliers / Customers

  • Suppliers:
  • Customers:

History

  • 2020 - McConnell Dowell awarded jetty contract
  • 2021 - First Gen signed charter agreement for FRSU

Other Information

-

Links

  1. McConnell Dowell Awarded Contracts and Granted Notice to Proceed by First Gen for Batangas LNG Terminal Project
  2. FGEN LNG Corporation enters 5-year contract for BW Paris