* 2013 - Project launched
 
* 2019 - Commercial operations began
 
* 2019 - Commercial operations began
 +
* 2020 - Final train began operations
  
 
=== Other Information ===
 
=== Other Information ===

Revision as of 08:34, 4 June 2021

Summary Information

  • Ownership: Kinder Morgan, Inc. (NYSE: KMI) and EIG Global Energy Partners (EIG)
  • Website: https://www.kindermorgan.com/
  • Location:
  • Capacity: million tons/annum
  • Status: In Operation

Brief Description

  • Elba Island LNG (Elba) is an innovative and flexible small-scale liquefaction plant, with 10 identical Movable Modular Liquefaction units. The facility has a total capacity of approximately 2.5 million tonnes per year of LNG for export, which is equivalent to approximately 350 million cubic feet (MMcf) per day of natural gas. Elba is directly connected to Southern LNG, which provides LNG storage, vaporization and ship loading services.

Technical Details

  • Storage capacity:
  • Constructor:
    • IHI: Pre-FEED, FEED, EPC, commissioning and start-up
  • Licensor:

Ongoing Projects/Project Status

  • The first phase of the terminal was commissioned in 2019

Suppliers / Customers

  • Suppliers:
  • Customers:

History

  • 2013 - Project launched
  • 2019 - Commercial operations began
  • 2020 - Final train began operations

Other Information

  • -

Relevant Links

  1. Terminal webpage
  2. IHI, project page