Abarrelfull (talk | contribs) (Created page with "Summary Information Ownership: IndianOil Website: http://www.iocl.com/ Location: Ennore, India Capacity: 5.0 million tons/annum Status: Under construction Brief Description A...") |
Abarrelfull (talk | contribs) |
||
Line 1: | Line 1: | ||
− | Summary Information | + | === Summary Information === |
− | Ownership: IndianOil | + | |
− | Website: http://www.iocl.com/ | + | * Ownership: IndianOil |
− | Location: Ennore, India | + | * Website: http://www.iocl.com/ |
− | Capacity: 5.0 million tons/annum | + | * Location: Ennore, India |
− | Status: Under construction | + | * Capacity: 5.0 million tons/annum |
− | Brief Description | + | * Status: Under construction |
− | A small regasification unit, the terminal will initially have the capacity to handle five million metric tonnes per annum (MMTPA), expanding to 15 MMTPA in the future | + | |
− | Technical Details | + | +++ Brief Description |
− | Storage capacity: 2 * 180, | + | * A small regasification unit, the terminal will initially have the capacity to handle five million metric tonnes per annum (MMTPA), expanding to 15 MMTPA in the future |
− | Unloading capacity: | + | |
− | Send out capacity: | + | +++ Technical Details |
− | Constructor: | + | * Storage capacity: 2 * 180,000m^^3^^ tanks |
− | Tractebel: Consultancy services for the preparation of a detailed feasibility report | + | * Unloading capacity: |
− | MHI: Construction of LNG storage tanks | + | * Send out capacity: |
− | Ongoing Projects/Project Status | + | * Constructor: |
− | Under construction | + | * **Tractebel:** Consultancy services for the preparation of a detailed feasibility report |
− | IOCL have awarded the contract for front-end engineering and design (FEED) study to Foster Wheeler | + | * **MHI:** Construction of LNG storage tanks |
− | Completion expected 2018 | + | |
− | Suppliers / Customers | + | |
− | Suppliers: | + | +++ Ongoing Projects/Project Status |
− | Customers: A 1000 MW LNG based Power plant on the same site will be the anchor customer | + | * Under construction |
− | History | + | * IOCL have awarded the contract for front-end engineering and design (FEED) study to Foster Wheeler |
− | 2010 - IndianOil signs MoU with TIDCO | + | * Completion expected 2018 |
− | 2012 - Foster Wheeler Awarded Contract for basic design, front-end engineering design, and the preparation of capital and operating cost estimates | + | |
− | 2015 - MHI awarded tank construction contract | + | +++ Suppliers / Customers |
− | Other Information | + | * Suppliers: |
− | - | + | * Customers: A 1000 MW LNG based Power plant on the same site will be the anchor customer |
− | + | ||
− | Tractebel Engineering LNG References | + | |
− | IndianOil signs MoU with TIDCO for Ennore LNG Project | + | +++ History |
− | Indian Oil in talks with Dhamra port for LNG terminal | + | * 2010 - IndianOil signs MoU with TIDCO |
− | Foster Wheeler Awarded Contract for an LNG Receiving Terminal in India | + | * 2012 - Foster Wheeler Awarded Contract for basic design, front-end engineering design, and the preparation of capital and operating cost estimates |
− | MHI Receives Order for 2 LNG Storage Tanks from IndianOil | + | * 2015 - MHI awarded tank construction contract |
+ | |||
+ | +++ Other Information | ||
+ | * - | ||
+ | |||
+ | === Links === | ||
+ | # [[Tractebel Engineering LNG References]] | ||
+ | # [http://www.iocl.com/aboutus/NewsDetail.aspx?NewsID=9202&tID=8 IndianOil signs MoU with TIDCO for Ennore LNG Project] | ||
+ | # [http://economictimes.indiatimes.com/news/news-by-industry/energy/oil-gas/indian-oil-in-talks-with-dhamra-port-for-lng-terminal/articleshow/11107829.cms Indian Oil in talks with Dhamra port for LNG terminal] | ||
+ | # [http://killajoules.wikidot.com/blog:1941 Foster Wheeler Awarded Contract for an LNG Receiving Terminal in India] | ||
+ | # [http://killajoules.wikidot.com/blog:5949 MHI Receives Order for 2 LNG Storage Tanks from IndianOil] |
Revision as of 16:37, 17 January 2022
Summary Information
- Ownership: IndianOil
- Website: http://www.iocl.com/
- Location: Ennore, India
- Capacity: 5.0 million tons/annum
- Status: Under construction
+++ Brief Description
- A small regasification unit, the terminal will initially have the capacity to handle five million metric tonnes per annum (MMTPA), expanding to 15 MMTPA in the future
+++ Technical Details
- Storage capacity: 2 * 180,000m^^3^^ tanks
- Unloading capacity:
- Send out capacity:
- Constructor:
* **Tractebel:** Consultancy services for the preparation of a detailed feasibility report * **MHI:** Construction of LNG storage tanks
+++ Ongoing Projects/Project Status
- Under construction
- IOCL have awarded the contract for front-end engineering and design (FEED) study to Foster Wheeler
- Completion expected 2018
+++ Suppliers / Customers
- Suppliers:
- Customers: A 1000 MW LNG based Power plant on the same site will be the anchor customer
+++ History
- 2010 - IndianOil signs MoU with TIDCO
- 2012 - Foster Wheeler Awarded Contract for basic design, front-end engineering design, and the preparation of capital and operating cost estimates
- 2015 - MHI awarded tank construction contract
+++ Other Information
- -