Summary Information

Ownership: Sempra Website: http://www.sempralng.com/ Location: On the Calcasieu Channel, 18 miles from the Gulf of Mexico in Hackberry, Louisiana Capacity: 12.0 million tons/annum Status: Planned Brief Description

A conversion of the existing Cameron LNG Terminal into a large liquifaction terminal Cameron plans to construct three separate systems that liquefy natural gas; one 160,000-cubic-meter, full-containment LNG storage tank; refrigerant make-up and condensate product storage; a truck loading/unloading area; one marine work dock; minor modifications to existing terminal facilities; 21 miles of 42-inch-diameter pipeline; one 56,820-horsepower compressor station; and ancillary facilities. Technical Details

Storage capacity: Four full-containment storage tanks (4 x 160,000 cubic meters) (One additional tank) Constructor: Foster Wheeler: Owner's Engineer Contract Tractebel: review of FEED LNG liquefaction/process package CB&I and Chiyoda: Engineering, procurement and construction for the addition of natural gas liquefaction and export facilities Licence: Air Products Ongoing Projects/Project Status

Commissioning is expected in 2018 Suppliers / Customers

Suppliers: Customers: GDF SUEZ will buy 4 million tons per annum (MTPA) TEPCO will buy 800,000 tons per annum (MTPA) Toho Gas will buy 300,000 tons per annum CPC of Taiwan will buy 0.8 million tons per annum History

2012 - Foster Wheeler Wins Owner's Engineer Contract 2012 - GDF-Suez signs purchase agreement 2013 - Tepco signs a purchase contract 2013 - Sempra Energy, GDF SUEZ, Mitsubishi, Mitsui Sign Tolling Capacity, Joint-Venture Agreement 2014 - Draft environmental impact statement released 2014 - Export permits granted 2014 - EPC contract awarded 2014 - FERC issues Final Environmental Impact Statement 2014 - FID made 2014 - Construction started Other Information

- Relevant Links

Tractebel Engineering LNG References Foster Wheeler Wins Owner's Engineer Contract for LNG Liquefaction Facility in Louisiana GDF SUEZ signs an agreement with Sempra Energyto access natural gas liquefaction capacity in the United States Purchase of Lean LNG from the U.S. Cameron Project Basic Agreement on the First Project to Secure 10 Million Lean LNG Annually Sempra Energy, GDF SUEZ, Mitsubishi, Mitsui Sign Tolling Capacity, Joint-Venture Agreements For Louisiana Liquefaction Export Facility GDF SUEZ to become a U.S. LNG exporter, with the Cameron LNG project DEIS on Cameron LNG, LLC’s and Cameron Interstate Pipeline, LLC’s Liquefaction Project Toho Gas in agreement with the U.S. Cameron Project for LNG purchase Sempra Energy Subsidiary Receives U.S. Department of Energy LNG Export License For Louisiana Liquefaction Facility CB&I and Chiyoda Awarded Contract for LNG Liquefaction and Export Facilities First GDF SUEZ long term LNG sale to Asia with a 0.8 mtpa contract to CPC of Taiwan FERC issues Final Environmental Impact Statement on Cameron LNG First GDF SUEZ long term LNG sales to Japan GDF SUEZ and its partners take Final Investment Decision for the Cameron LNG project Cameron LNG Liquefaction Project Breaks Ground In Louisiana Air Products Wins LNG Technology and Equipment Order for Louisiana Terminal Facility