Difference between revisions of "Algiers El Harrach Refinery Project"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 8: | Line 8: | ||
** After: 3.6 million tons/annum & 72,000 bbl/day | ** After: 3.6 million tons/annum & 72,000 bbl/day | ||
* Nelson Complexity: | * Nelson Complexity: | ||
− | * Project Stage: Completed | + | * Project Stage: Completed 2019 |
* Budget: USD 908 million | * Budget: USD 908 million | ||
+ | |||
=== The Project === | === The Project === | ||
* Project Type: Upgrade and debottlenecking | * Project Type: Upgrade and debottlenecking |
Latest revision as of 16:28, 16 March 2020
Contents
Summary Information
- Ownership: Sonatrach
- Website: http://www.sonatrach-dz.com/ (French)
- Wiki Page: El Harrach Refinery
- Location: Algiers, Algeria
- Capacity:
- Before: 2.7 million tons/annum & 54,000 bbl/day
- After: 3.6 million tons/annum & 72,000 bbl/day
- Nelson Complexity:
- Project Stage: Completed 2019
- Budget: USD 908 million
The Project
- Project Type: Upgrade and debottlenecking
- Project Summary: A refurbishment and revamping of the existing units plus the addition of gasoline specification units
- Main Contractors
- Technip: Lump sum turnkey contract for the complete scope of works, including the design, supply of equipment and bulk material, construction and start-up
Refining Units
- Topping and gas plant capacity increase.
- New MS Block (NHT + Isom + CCR Reforming)
- RFCC and Merox Units
- Rehabilitation of Utility production and distribution facilities
- Moderniztion of the Instrumentation (implementation of DCS with a centralized control room)
- Rehabilitation of electrical equipment, upgrading of electrical network, and setting up of a gas turbine,
- New Waste Water Treatment Unit (biological type)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
-
Products Produced
- Gasoline meeting Euro standards
History
- 2010 - Technip awarded LSTK contract for project
- 2013 - Emerson awarded valve supply contract
- 2016 - CPECC awarded the project
- 2020 - Project completed
Other Information
- The contract with Technip was cancelled and they were replaced by CPECC